FDOT Pipeline Changes - October 2026
- The total active project count increased by 7, from 339 to 346.
- Pipeline costs rose slightly by 0.5%, with a total value of $1.30B.
- District 6 saw the largest net cost increase at +$13.12M.
Overview
Looking at FDOT project revisions that occurred October 13, through October 26, 2026, across a letting window of October 1, 2026 to January 1, 2029, the active project pipeline reflects a slight increase in both project count and pipeline value. There were no significant shifts in letting dates, with most projects maintaining their original schedules. The types and subtypes are stable, while costs show minor adjustments across various projects.
Letting Date Shifts (Slippage)
💡 How to read this chart:
No projects shifted by 6 months or more during this period. Recent lettings have mostly remained unchanged, indicating that the project timelines are generally stable.
| CSJ | District | Est. Letting Date | Project Estimate | Current Type | Current Subtype | Prev. Type | Prev. Subtype | Prev. Date | Letting Δ (days) | Letting Date Δ | Cost Δ | %Cost Δ | Type/Subtype Δ | Lifecycle |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 453086 1 | District 5 | 05/19/27 | $2,503,000.00 | 01/27/27 | 112 | 4 months | ||||||||
| 429528 6 | District 4 | 12/11/26 | $1,234,000.00 | 10/09/26 | 63 | 2 months | ||||||||
| 207850 2 | District 2 | 04/21/27 | $37,829,000.00 | 03/17/27 | 35 | 1 month | $4,000.00 | 0% | ||||||
| 447928 1 | District 7 | 03/31/27 | $16,522,000.00 | 02/24/27 | 35 | 1 month | ||||||||
| 449153 1 | District 7 | 03/31/27 | $7,335,000.00 | 02/24/27 | 35 | 1 month | ||||||||
| 454038 1 | District 7 | 02/10/27 | $1,514,000.00 | 03/10/27 | -28 | -28 days | ||||||||
| 455329 1 | District 7 | 02/10/27 | $1,117,000.00 | 03/10/27 | -28 | -28 days | ||||||||
| 435384 2 | District 4 | 05/19/27 | $28,543,000.00 | 05/26/27 | -7 | -7 days | ||||||||
| 449815 1 | District 4 | 05/19/27 | $6,541,000.00 | 05/26/27 | -7 | -7 days | ||||||||
| 453147 1 | District 4 | 05/19/27 | $1,729,000.00 | 05/26/27 | -7 | -7 days | ||||||||
| 435461 5 | Turnpike | 11/17/26 | $118,000,000.00 | Roadway | Roadway Widening & New Roadway | Roadway | Roadway Widening & New Roadway | 11/10/26 | 7 | 7 days | ||||
| 437155 1 | Turnpike | 11/03/26 | $247,885,000.00 | 10/27/26 | 7 | 7 days | $8,000.00 | 0% |
Project Type & Subtype Changes
The project type and subtype mix has remained stable, with 22 documented type/subtype changes. Notably, the most frequent transition involved projects moving from unclassified to Bridge or Bridge Maintenance & Rehabilitation.
| CSJ | District | Est. Letting Date | Project Estimate | Current Type | Current Subtype | Type/Subtype Δ | Prev. Type | Prev. Subtype | Prev. Cost | Prev. Date | Letting Δ (days) | Letting Date Δ | Cost Δ | %Cost Δ | Lifecycle |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 423373 6 | Turnpike | 11/10/26 | $1,845,000.00 | Bridge | Bridge Maintenance & Rehabilitation | Unassigned → Bridge / Bridge Maintenance & Rehabilitation | Unassigned | Unassigned | $1,845,000.00 | 11/10/26 | 0 | ||||
| 452085 1 | Turnpike | 11/10/26 | $3,682,000.00 | Bridge | Bridge Maintenance & Rehabilitation | Unassigned → Bridge / Bridge Maintenance & Rehabilitation | Unassigned | Unassigned | $3,682,000.00 | 11/10/26 | 0 | ||||
| 452109 1 | Turnpike | 11/10/26 | $2,636,000.00 | Roadway | Roadway Rehabilitation & Street Reconstruction | Unassigned → Roadway / Roadway Rehabilitation & Street Reconstruction | Unassigned | Unassigned | $2,636,000.00 | 11/10/26 | 0 | ||||
| 453815 1 | Turnpike | 11/10/26 | $2,333,000.00 | Traffic & Safety | Traffic Signals, ITS & Roadway Lighting | Unassigned → Traffic & Safety / Traffic Signals, ITS & Roadway Lighting | Unassigned | Unassigned | $2,333,000.00 | 11/10/26 | 0 | ||||
| E8X24-R0 | 11/10/26 | Maintenance & Services | Roadside Mowing, Vegetation & Litter | Unassigned → Maintenance & Services / Roadside Mowing, Vegetation & Litter | Unassigned | Unassigned | Unassigned | ||||||||
| E8X26-R0 | 11/10/26 | Maintenance & Services | Roadside Mowing, Vegetation & Litter | Unassigned → Maintenance & Services / Roadside Mowing, Vegetation & Litter | Unassigned | Unassigned | Unassigned | ||||||||
| E8X27-R0 | 11/10/26 | Maintenance & Services | Roadside Mowing, Vegetation & Litter | Unassigned → Maintenance & Services / Roadside Mowing, Vegetation & Litter | Unassigned | Unassigned | Unassigned | ||||||||
| E8X35 | District 4 | 11/10/26 | Facilities | Facility Systems, Repair & Abatement | Unassigned → Facilities / Facility Systems, Repair & Abatement | Unassigned | Unassigned | Unassigned | |||||||
| E8X36 | District 4 | 11/10/26 | Facilities | Facility Systems, Repair & Abatement | Unassigned → Facilities / Facility Systems, Repair & Abatement | Unassigned | Unassigned | Unassigned | |||||||
| 453332 1 | District 3 | 11/13/26 | $4,089,000.00 | Roadway | Roadway Rehabilitation & Street Reconstruction | Unassigned → Roadway / Roadway Rehabilitation & Street Reconstruction | Unassigned | Unassigned | $4,089,000.00 | 11/13/26 | 0 | ||||
| 454170 1 | District 3 | 11/13/26 | $1,714,000.00 | Traffic & Safety | Traffic Signals, ITS & Roadway Lighting | Unassigned → Traffic & Safety / Traffic Signals, ITS & Roadway Lighting | Unassigned | Unassigned | $1,714,000.00 | 11/13/26 | 0 | ||||
| 454408 1 | District 3 | 11/13/26 | $468,000.00 | Bridge | Bridge Maintenance & Rehabilitation | Unassigned → Bridge / Bridge Maintenance & Rehabilitation | Unassigned | Unassigned | $468,000.00 | 11/13/26 | 0 | ||||
| 456985 1 | District 3 | 11/13/26 | $155,000.00 | Maintenance & Services | Landscaping, Grounds & Facility Services | Unassigned → Maintenance & Services / Landscaping, Grounds & Facility Services | Unassigned | Unassigned | $155,000.00 | 11/13/26 | 0 | ||||
| 457757 1 | District 3 | 11/13/26 | $340,000.00 | Maintenance & Services | Landscaping, Grounds & Facility Services | Unassigned → Maintenance & Services / Landscaping, Grounds & Facility Services | Unassigned | Unassigned | $340,000.00 | 11/13/26 | 0 | ||||
| E3Z90-R0 | District 3 | 11/13/26 | $661,802.00 | Maintenance & Services | Roadside Mowing, Vegetation & Litter | Unassigned → Maintenance & Services / Roadside Mowing, Vegetation & Litter | Unassigned | Unassigned | Unassigned | $661,802.00 | |||||
| E3Z97-R0 | District 3 | 11/13/26 | $350,000.00 | Traffic & Safety | Signs, Pavement Markings & Striping | Unassigned → Traffic & Safety / Signs, Pavement Markings & Striping | Unassigned | Unassigned | Unassigned | $350,000.00 | |||||
| E3Z98 | District 3 | 11/13/26 | $1,015,000.00 | Traffic & Safety | Signs, Pavement Markings & Striping | Unassigned → Traffic & Safety / Signs, Pavement Markings & Striping | Unassigned | Unassigned | Unassigned | $1,015,000.00 | |||||
| Z3045-R0 | District 3 | 11/13/26 | Traffic & Safety | Traffic Signals, ITS & Roadway Lighting | Unassigned → Traffic & Safety / Traffic Signals, ITS & Roadway Lighting | Unassigned | Unassigned | Unassigned | |||||||
| 457506 1 | Turnpike | 11/17/26 | $5,357,000.00 | Bridge | Bridge Maintenance & Rehabilitation | Unassigned → Bridge / Bridge Maintenance & Rehabilitation | Unassigned | Unassigned | $5,357,000.00 | 11/17/26 | 0 | ||||
| 408867 2 | District 2 | 11/18/26 | $1,326,000.00 | Roadway | Roadway Rehabilitation & Street Reconstruction | Unassigned → Roadway / Roadway Rehabilitation & Street Reconstruction | Unassigned | Unassigned | $1,326,000.00 | 11/18/26 | 0 | ||||
| 443652 2 | District 2 | 11/18/26 | $408,000.00 | Maintenance & Services | Landscaping, Grounds & Facility Services | Unassigned → Maintenance & Services / Landscaping, Grounds & Facility Services | Unassigned | Unassigned | $408,000.00 | 11/18/26 | 0 | ||||
| E22A6 | District 2 | 11/18/26 | $300,000.00 | Active Transportation | Pedestrian, Bicycle & Concrete Flatwork | Unassigned → Active Transportation / Pedestrian, Bicycle & Concrete Flatwork | Unassigned | Unassigned | Unassigned | $300,000.00 |
Cost Changes
The pipeline value increased by $6.21M to $1.30B. Cost adjustments were seen across project subtypes, with District 6 realizing a net increase of $13.12M, while the Turnpike experienced a decrease of $12.10M.
| CSJ | District | Est. Letting Date | Project Estimate | Current Type | Current Subtype | Prev. Type | Prev. Subtype | Prev. Cost | Cost Δ | %Cost Δ | Letting Δ (days) | Letting Date Δ | Type/Subtype Δ | Lifecycle |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 441715 1 | District 4 | 01/27/27 | $6,032,000.00 | $10,831,000.00 | $(4,799,000.00) | -44% | 0 | |||||||
| E3Z86-R0 | District 3 | 10/08/26 | $150,000.00 | Traffic & Safety | Signs, Pavement Markings & Striping | Traffic & Safety | Signs, Pavement Markings & Striping | $268,800.00 | $(118,800.00) | -44% | 0 | |||
| E3Z85-R0 | District 3 | 10/08/26 | $50,000.00 | Traffic & Safety | Signs, Pavement Markings & Striping | Traffic & Safety | Signs, Pavement Markings & Striping | $85,200.00 | $(35,200.00) | -41% | 0 | |||
| 458235 2 | District 4 | 01/08/27 | $1,106,000.00 | $1,621,000.00 | $(515,000.00) | -32% | 0 | |||||||
| 451480 1 | District 1 | 10/15/26 | $2,574,000.00 | $3,676,000.00 | $(1,102,000.00) | -30% | 0 | |||||||
| 441714 1 | District 4 | 01/27/27 | $10,840,000.00 | $15,301,000.00 | $(4,461,000.00) | -29% | 0 | |||||||
| 453144 1 | District 4 | 03/31/27 | $2,375,000.00 | $3,273,000.00 | $(898,000.00) | -27% | 0 | |||||||
| 449691 1 | District 4 | 10/09/26 | $18,988,000.00 | Bridge | Bridge Maintenance & Rehabilitation | Bridge | Bridge Maintenance & Rehabilitation | $15,139,000.00 | $3,849,000.00 | 25% | 0 | |||
| 453148 1 | District 4 | 02/24/27 | $2,415,000.00 | $3,165,000.00 | $(750,000.00) | -24% | 0 | |||||||
| 452633 1 | District 5 | 10/06/26 | $1,485,000.00 | Roadway | Roadway Rehabilitation & Street Reconstruction | Roadway | Roadway Rehabilitation & Street Reconstruction | $1,946,000.00 | $(461,000.00) | -24% | 0 | |||
| 430132 7 | District 5 | 03/02/27 | $2,155,000.00 | $2,789,000.00 | $(634,000.00) | -23% | 0 | |||||||
| 449814 1 | District 4 | 01/08/27 | $964,000.00 | $1,237,000.00 | $(273,000.00) | -22% | 0 | |||||||
| 413065 2 | District 1 | 10/15/26 | $1,514,000.00 | $1,921,000.00 | $(407,000.00) | -21% | 0 | |||||||
| 452648 1 | District 5 | 10/06/26 | $2,032,000.00 | Roadway | Roadway Rehabilitation & Street Reconstruction | Roadway | Roadway Rehabilitation & Street Reconstruction | $2,500,000.00 | $(468,000.00) | -19% | 0 | |||
| 448436 1 | District 4 | 01/08/27 | $2,921,000.00 | $3,531,000.00 | $(610,000.00) | -17% | 0 | |||||||
| 436194 3 | Turnpike | 04/20/27 | $117,500,000.00 | $136,666,000.00 | $(19,166,000.00) | -14% | 0 | |||||||
| 448106 1 | District 4 | 12/02/26 | $2,499,000.00 | $2,883,000.00 | $(384,000.00) | -13% | 0 | |||||||
| 441143 2 | District 5 | 03/31/27 | $10,275,000.00 | $9,147,000.00 | $1,128,000.00 | 12% | 0 | |||||||
| 455697 2 | District 3 | 04/28/27 | $5,713,000.00 | $6,472,000.00 | $(759,000.00) | -12% | 0 | |||||||
| 452921 1 | District 4 | 03/31/27 | $3,355,000.00 | $3,795,000.00 | $(440,000.00) | -12% | 0 | |||||||
| 433726 3 | District 1 | 10/15/26 | $285,000.00 | $321,000.00 | $(36,000.00) | -11% | 0 | |||||||
| 447166 1 | District 2 | 03/31/27 | $468,000.00 | $429,000.00 | $39,000.00 | 9% | 0 | |||||||
| 452942 1 | District 4 | 03/31/27 | $4,662,000.00 | $4,331,000.00 | $331,000.00 | 8% | 0 | |||||||
| 448825 1 | District 2 | 04/28/27 | $40,645,000.00 | $43,935,000.00 | $(3,290,000.00) | -7% | 0 | |||||||
| 429930 1 | District 2 | 03/31/27 | $17,474,000.00 | $18,842,000.00 | $(1,368,000.00) | -7% | 0 | |||||||
| 456151 1 | Turnpike | 02/09/27 | $4,672,000.00 | $5,007,000.00 | $(335,000.00) | -7% | 0 | |||||||
| 213273 8 | District 2 | 02/24/27 | $8,294,000.00 | $8,858,000.00 | $(564,000.00) | -6% | 0 | |||||||
| 447106 2 | District 5 | 03/31/27 | $6,341,000.00 | $6,008,000.00 | $333,000.00 | 6% | 0 | |||||||
| 449819 1 | District 4 | 03/31/27 | $23,962,000.00 | $25,356,000.00 | $(1,394,000.00) | -6% | 0 | |||||||
| 453545 1 | District 5 | 05/19/27 | $16,532,000.00 | $17,475,000.00 | $(943,000.00) | -5% | 0 | |||||||
| 445435 1 | District 2 | 03/31/27 | $1,479,000.00 | $1,557,000.00 | $(78,000.00) | -5% | 0 | |||||||
| 453142 1 | District 4 | 04/28/27 | $552,000.00 | $526,000.00 | $26,000.00 | 5% | 0 | |||||||
| 455434 1 | District 4 | 03/05/27 | $7,439,000.00 | $7,768,000.00 | $(329,000.00) | -4% | 0 | |||||||
| 457180 1 | District 4 | 03/31/27 | $7,961,000.00 | $8,310,000.00 | $(349,000.00) | -4% | 0 | |||||||
| 454101 1 | District 6 | 04/28/27 | $14,669,000.00 | $14,177,000.00 | $492,000.00 | 3% | 0 | |||||||
| 449834 1 | District 4 | 03/31/27 | $3,498,000.00 | $3,388,000.00 | $110,000.00 | 3% | 0 | |||||||
| 417132 1 | Turnpike | 02/09/27 | $276,584,000.00 | $269,195,000.00 | $7,389,000.00 | 3% | 0 | |||||||
| 450435 1 | District 5 | 01/27/27 | $1,214,000.00 | $1,237,000.00 | $(23,000.00) | -2% | 0 | |||||||
| 451188 1 | District 6 | 03/25/27 | $646,000.00 | $656,000.00 | $(10,000.00) | -2% | 0 | |||||||
| 209469 4 | District 2 | 02/24/27 | $10,104,000.00 | $10,243,000.00 | $(139,000.00) | -1% | 0 | |||||||
| 451103 1 | District 1 | 12/03/26 | $6,339,000.00 | $6,409,000.00 | $(70,000.00) | -1% | 0 | |||||||
| 430132 2 | District 5 | 03/02/27 | $42,155,000.00 | $42,040,000.00 | $115,000.00 | 0% | 0 | |||||||
| 444415 1 | District 4 | 12/02/26 | $1,442,000.00 | $1,439,000.00 | $3,000.00 | 0% | 0 | |||||||
| 446445 5 | District 5 | 01/27/27 | $48,767,000.00 | $48,692,000.00 | $75,000.00 | 0% | 0 | |||||||
| 207850 2 | District 2 | 04/21/27 | $37,829,000.00 | $37,825,000.00 | $4,000.00 | 0% | 35 | 1 month | ||||||
| 437155 1 | Turnpike | 11/03/26 | $247,885,000.00 | $247,877,000.00 | $8,000.00 | 0% | 7 | 7 days | ||||||
| 210265 8 | District 2 | 10/28/26 | $6,742,000.00 | Roadway | Roadway Rehabilitation & Street Reconstruction | Roadway | Roadway Rehabilitation & Street Reconstruction | $6,742,000.00 | $0.00 | 0% | 0 | |||
| 440816 7 | District 5 | 10/06/26 | $4,279,000.00 | Traffic & Safety | Traffic Signals, ITS & Roadway Lighting | Traffic & Safety | Traffic Signals, ITS & Roadway Lighting | $4,279,000.00 | $0.00 | 0% | 0 | |||
| 452912 1 | District 5 | 10/06/26 | $5,455,000.00 | Roadway | Roadway Rehabilitation & Street Reconstruction | Roadway | Roadway Rehabilitation & Street Reconstruction | $5,455,000.00 | $0.00 | 0% | 0 |
Final Takeaway
This suggests a generally steady pipeline with slight growth and minor adjustments in project costs.