  • The TxDOT pipeline expanded from 6,282 to 6,414 total projects between the April 3 and May 4, 2026 snapshots, within a letting window from May 5, 2026 to March 1, 2029.
  • Overall pipeline value increased by $163.98 million to a total of $6.71 billion.
  • The largest cost movement occurred in Dallas with a net increase of $63.49 million.

Overview

Comparing how the project pipeline changed from April 3 to May 4, 2026, across a letting window of May 5, 2026 to March 1, 2029, there was significant activity. The total number of projects increased from 6,282 to 6,414. Letting dates reflected a drift with 211 projects shifting by six months or more, of which 142 moved later and 69 moved earlier. The overall pipeline value grew to $6.71 billion, indicating a shift in funding focus.


Letting Date Shifts (Slippage)

Project letting dates experienced notable shifts, with 211 projects having changes of six months or more, 142 moved later while 69 moved earlier. There were 130 projects with shifts of a year or more, 96 later and 34 earlier. This suggests that many projects are being deferred, contributing to a later project delivery schedule.

CSJDistrictEst. Letting DateProject EstimateCurrent TypeCurrent SubtypePrev. TypePrev. SubtypePrev. DateLetting Δ (days)Letting Date ΔCost Δ%Cost ΔType/Subtype ΔAdvertised ΔLifecycle
2664-01-007Lufkin10/04/28$4,882,572.05ConstructionRoadwayUnassignedUnassigned09/01/45-6176-17 yearsUnassigned → Construction / Roadway
0495-08-107Atlanta01/01/39$5,357,426.00ConstructionRoadway01/05/28401411 years
0495-10-090Atlanta01/01/39$7,841,466.00ConstructionRoadway01/05/28401411 years
0495-10-103Atlanta01/01/39$5,466,829.00ConstructionRoadway01/05/28401411 years
0495-10-104Atlanta01/01/39$8,713,538.00ConstructionRoadway01/05/28401411 years
0610-03-089Atlanta01/01/39$8,377,828.00ConstructionRoadway01/05/28401411 years
0610-05-052Atlanta01/01/39$7,638,133.00ConstructionRoadway01/05/28401411 years
0610-06-094Atlanta01/01/39$6,602,181.00ConstructionRoadway01/05/28401411 years
0610-06-095Atlanta01/01/39$5,452,059.00ConstructionRoadway01/05/28401411 years
0275-16-004Amarillo11/01/37$170,000.00ConstructionRoadway11/02/27365210 years
1092-01-026Dallas05/05/27$12,239,522.17ConstructionRoadwayUnassignedUnassigned08/01/35-3010-8 yearsUnassigned → Construction / Roadway
3510-03-003Houston01/15/37$55,381,565.0001/15/2929228 years
0558-09-040San Angelo06/01/35$13,200,000.00ConstructionRoadway06/01/2825567 years
0007-03-099Brownwood11/02/27$587,822.00ConstructionRoadwayUnassignedUnassigned11/01/34-2556-7 yearsUnassigned → Construction / Roadway
0007-03-100Brownwood11/02/27$590,391.00ConstructionRoadwayUnassignedUnassigned11/01/34-2556-7 yearsUnassigned → Construction / Roadway
1014-02-051Dallas10/01/35$548,755.00ConstructionRoadway10/04/2825537 years
2263-02-112Corpus Christi10/01/35$17,000,000.00ConstructionFerry Boat10/04/2825537 years
0997-01-051Dallas10/01/33$534,725.65ConstructionRoadway10/06/2625527 years
0999-01-049Dallas10/01/33$271,147.24ConstructionRoadway10/06/2625527 years
2462-04-009Dallas10/01/33$452,799.26ConstructionRoadway10/06/2625527 years
0520-05-054Atlanta08/02/28$3,500,000.00ConstructionRoadwayUnassignedUnassigned01/01/35-2343-6 years$(14,000,000.00)-80%Unassigned → Construction / Roadway
0143-14-006San Antonio09/06/28$6,540,250.00ConstructionRoadwayUnassignedUnassigned01/01/35-2308-6 yearsUnassigned → Construction / Roadway
0183-01-059Brownwood11/01/32$14,114.00ConstructionRoadway11/03/2621906 years
0047-04-042Dallas10/01/34$420,992.25ConstructionRoadway10/04/2821886 years
2170-05-018Laredo02/02/28$2,000,000.00ConstructionRoadwayUnassignedUnassigned11/01/33-2099-6 years$1,600,000.00400%Unassigned → Construction / Roadway
0521-05-144San Antonio09/01/27$589,100,000.00ConstructionRoadwayUnassignedUnassigned09/01/32-1827-5 yearsUnassigned → Construction / Roadway
2013-02-018Brownwood11/01/31$11,626.00ConstructionRoadway11/03/2618245 years
0337-02-055Austin10/02/30$945,350.00ConstructionLocal Let10/01/2614624 years
0088-02-070Corpus Christi12/01/31$1,000,000.00ConstructionNon Roadway12/01/2714614 years
0447-03-043Corpus Christi12/01/31$1,500,000.00ConstructionNon Roadway12/01/2714614 years
0912-71-692Houston09/15/30$15,000.00Non-LetRoadway09/15/2614614 years
0912-72-005Houston09/15/30$30,000.00Non-LetRoadway09/15/2614614 years
0054-04-119Brownwood11/01/28$454,880.00ConstructionRoadwayUnassignedUnassigned11/01/32-1461-4 yearsUnassigned → Construction / Roadway
0070-06-053Brownwood11/01/28$263,697.00ConstructionRoadwayUnassignedUnassigned11/01/32-1461-4 yearsUnassigned → Construction / Roadway
2270-01-030Abilene05/03/28$1,666,666.67ConstructionRoadwayUnassignedUnassigned05/01/32-1459-4 years$(565,476.33)-25%Unassigned → Construction / Roadway
0007-06-269Brownwood11/03/26$131,061.00ConstructionRoadwayUnassignedUnassigned11/01/30-1459-4 yearsUnassigned → Construction / Roadway
0007-06-272Brownwood11/03/26$131,061.00ConstructionRoadwayUnassignedUnassigned11/01/30-1459-4 yearsUnassigned → Construction / Roadway
0523-01-032Houston03/01/32$961,403.00ConstructionRoadway03/07/2814554 years
0367-02-084Houston09/01/31$500,000.00ConstructionRoadway03/07/2812733 years$(1,406,590.00)-74%
0014-23-042Waco10/06/26$6,000,000.00ConstructionRoadwayUnassignedUnassigned02/01/30-1214-3 years$(4,000,000.00)-40%Unassigned → Construction / Roadway
0756-05-021Lufkin09/01/31$6,440,000.00ConstructionBridge06/01/2811873 years
0038-01-089Laredo02/01/31$2,261,754.60ConstructionRoadway02/02/2810953 years
0086-14-104Laredo02/01/31$4,493,788.95ConstructionRoadway02/02/2810953 years
2786-01-020Brownwood11/01/29$23,985.00ConstructionRoadway11/03/2610943 years
0870-06-025Brownwood05/01/31$4,048,369.20ConstructionRoadway05/03/2810933 years
0999-01-048Dallas08/01/30$7,921,726.91ConstructionRoadway08/04/2710933 years
1003-01-098Houston09/01/31$1,088,146.00ConstructionRoadway09/06/2810903 years$(23,057,977.00)-95%
0843-06-020Atlanta02/01/29$3,751,667.00ConstructionRoadwayUnassignedUnassigned01/01/32-1064-3 yearsUnassigned → Construction / Roadway
0013-08-147Fort Worth06/01/27$54,615,384.64ConstructionRoadwayUnassignedUnassigned01/01/30-945-3 years$7,034,010.8815%Unassigned → Construction / Roadway
0014-15-087Fort Worth06/01/27$20,384,615.38ConstructionRoadwayUnassignedUnassigned01/01/30-945-3 years$5,826,381.5840%Unassigned → Construction / Roadway
0027-10-082Houston05/05/27$1,429,810.00ConstructionRoadwayUnassignedUnassigned12/01/29-941-3 yearsUnassigned → Construction / Roadway
2594-01-015Lufkin05/01/30$5,608,654.30ConstructionBridge10/05/279393 years
2374-05-092Fort Worth01/09/30$3,037,016.40ConstructionLocal Let11/09/277922 years
0063-04-069Atlanta01/06/27$5,242,917.00ConstructionRoadwayConstructionRoadway03/01/29-785-2 years
0063-05-041Atlanta01/06/27$3,257,083.00ConstructionRoadwayConstructionRoadway03/01/29-785-2 years
0978-02-092Houston11/01/29$17,357,933.00ConstructionRoadway10/05/277582 years
3049-01-037Houston11/01/29$64,696,185.00ConstructionRoadway10/05/277582 years
3049-01-038Houston11/01/29$33,838,904.00ConstructionRoadway10/05/277582 years
0378-06-024Tyler12/05/28$91,443.18ConstructionRoadwayConstructionRoadway12/01/267352 years
0187-05-063Houston09/06/28$3,674,142.32ConstructionNon RoadwayConstructionNon Roadway09/02/267352 years
1043-01-012Houston09/02/26$1,000,000.00ConstructionRoadwayConstructionRoadway09/06/28-735-2 years
1043-02-005Houston09/02/26$177,120.00ConstructionRoadwayConstructionRoadway09/06/28-735-2 years
3256-03-107Houston07/01/29$1,291,992.00ConstructionRoadwayConstructionRoadway07/01/277312 years
0300-01-111Laredo03/01/31$3,185,762.83ConstructionRoadway03/01/297302 years
1549-04-036Corpus Christi01/01/31$5,000,000.00ConstructionRoadway01/01/297302 years
0119-01-020Lufkin11/01/29$4,699,706.70ConstructionBridge11/02/277302 years
0743-02-029Lufkin11/01/29$4,925,806.28ConstructionBridge11/02/277302 years
0050-08-104Houston02/01/29$27,031,845.00ConstructionRoadwayConstructionRoadway02/02/277302 years
3022-02-009Dallas02/01/29$5,938,245.17ConstructionRoadwayConstructionRoadway02/02/277302 years$950,010.4919%
0109-08-052Lufkin11/02/27$1,126,844.19ConstructionRoadwayUnassignedUnassigned11/01/29-730-2 yearsUnassigned → Construction / Roadway
0720-02-098Houston03/03/27$7,639,008.00ConstructionRoadwayConstructionRoadway03/01/29-729-2 years
0815-03-016Dallas10/01/30$605,163.96ConstructionRoadway10/04/287272 years$536,313.96779%
0074-03-050Corpus Christi01/01/30$4,500,000.00ConstructionRoadway01/05/287272 years$1,100,000.0032%
0074-04-049Corpus Christi01/01/30$3,000,000.00ConstructionRoadway01/05/287272 years$900,000.0043%
2846-01-008Dallas12/01/30$6,759,240.62ConstructionRoadway12/05/287262 years$261,323.364%
0912-72-809Houston01/01/29$500,000.00ConstructionRail - SafetyConstructionRail - Safety01/06/277262 years
0069-01-061Abilene07/01/30$20,000,000.00ConstructionRoadway07/06/287252 years
0069-02-030San Angelo07/01/30$5,000,000.00ConstructionRoadway07/06/287252 years
0217-01-038Atlanta09/06/28$2,400,000.00ConstructionBridgeConstructionBridge10/06/267012 years
0051-03-123Houston08/01/29$9,073,088.00ConstructionRoadwayConstructionRoadway09/01/277002 years
0976-05-031Houston03/01/29$1,847,549.00ConstructionRoadwayConstructionRoadway04/06/276952 years
2977-01-011Dallas07/01/26$11,777,297.44ConstructionRoadwayConstructionRoadway05/03/28-672-2 years$(553,199.50)-4%
0138-08-034Tyler01/01/31$2,620,282.00ConstructionNon Roadway03/01/296712 years
1680-03-031Lufkin09/01/29$2,098,409.53ConstructionBridge11/02/276692 years
0912-72-812Houston09/15/28$500,000.00Non-LetRailConstructionRail - Safety12/01/266542 yearsConstruction / Rail - Safety → Non-Let / Rail
0070-03-062San Angelo07/01/26$3,599,697.00ConstructionRoadwayConstructionRoadway04/05/28-644-2 years$(1,026,460.00)-22%
0070-04-041San Angelo07/01/26$175,049.00ConstructionRoadwayConstructionRoadway04/05/28-644-2 years$36,849.0027%
0368-03-042Beaumont07/01/26$1,762,157.35ConstructionRoadwayConstructionRoadway04/05/28-644-2 years$262,157.3517%
0786-01-095Beaumont07/01/26$4,288,248.61ConstructionRoadwayConstructionRoadway04/05/28-644-2 years$(211,751.39)-5%
0118-08-085Lufkin06/01/30$5,554,561.67ConstructionBridge10/04/286052 years
0172-09-044Fort Worth08/02/28$2,582,000.00ConstructionRoadwayConstructionRoadway02/02/275471 year
0383-04-065Corpus Christi07/01/30$3,000,000.00ConstructionRoadway01/01/295461 year$(1,600,000.00)-35%
0008-07-034Fort Worth11/03/28$3,604,001.50ConstructionLocal LetConstructionLocal Let07/03/274891 year
0029-01-031San Antonio01/05/28$102,880.00ConstructionRoadwayConstructionRoadway10/06/264561 year
0366-12-033San Antonio01/05/28$90,889.00ConstructionRoadwayConstructionRoadway10/06/264561 year
1003-01-105Houston01/05/28$5,116,513.00ConstructionBridgeConstructionBridge10/06/264561 year
1385-01-046Atlanta01/05/28$600,000.00ConstructionRoadwayConstructionRoadway10/06/264561 year
1020-01-068Atlanta03/03/27$2,400,000.00ConstructionRoadwayConstructionRoadway06/01/28-456-1 year$598,270.0033%
0976-03-122Houston11/02/27$528,000.00ConstructionRoadwayConstructionRoadway09/02/264261 year
6487-61-001Houston09/02/27$1,000,000.00MaintenanceRoutine Maintenance ContractUnassignedUnassigned08/01/263971 yearUnassigned → Maintenance / Routine Maintenance Contract
0943-04-035Corpus Christi04/01/29$5,500,000.00ConstructionRoadwayConstructionRoadway03/07/283901 year
0912-00-704Houston09/15/27$1,000,000.00ConstructionLocal LetConstructionRail - Safety09/02/263781 yearConstruction / Rail - Safety → Construction / Local Let
0109-01-066Tyler09/06/28$3,800,000.00ConstructionRoadwayConstructionRoadway09/01/273711 year
0109-02-027Tyler09/06/28$3,250,000.00ConstructionRoadwayConstructionRoadway09/01/273711 year
0169-02-071Amarillo09/06/28$1,970,000.00ConstructionBridgeConstructionBridge09/01/273711 year
0169-02-072Amarillo09/06/28$1,500,000.00ConstructionBridgeConstructionBridge09/01/273711 year
2635-02-040Amarillo09/06/28$1,100,000.00ConstructionBridgeConstructionBridge09/01/273711 year
2635-02-041Amarillo09/06/28$1,140,000.00ConstructionBridgeConstructionBridge09/01/273711 year
0111-05-019Houston03/07/28$4,480,673.00ConstructionRoadwayConstructionRoadway03/03/273701 year
0847-06-013Houston03/07/28$3,919,359.00ConstructionRoadwayConstructionRoadway03/03/273701 year
0253-06-041San Antonio09/03/27$4,700,000.00Non-LetBridgeNon-LetBridge09/01/263671 year
0517-02-043San Antonio09/03/27$5,452,200.00Non-LetBridgeNon-LetBridge09/01/263671 year
0248-04-086Atlanta03/01/30$6,750,000.00ConstructionRoadway03/01/293651 year
0163-04-066Tyler02/01/30$12,300,000.00ConstructionRoadway02/01/293651 year
0192-04-113Houston02/01/30$7,570,207.00ConstructionRoadway02/01/293651 year
0495-02-072Tyler02/01/30$12,037,037.04ConstructionRoadway02/01/293651 year
0091-09-019Dallas01/01/30$8,932,684.66ConstructionRoadway01/01/293651 year$(2,862,848.38)-24%
0978-02-089Houston01/01/30$2,266,543.00ConstructionRoadway01/01/293651 year
1875-02-030Lufkin11/01/29$471,364.14ConstructionRoadway11/01/283651 year
0068-02-050Lubbock02/01/29$1,371,261.60ConstructionRoadwayUnassignedUnassigned02/01/30-365-1 yearUnassigned → Construction / Roadway
0192-04-110Houston01/01/29$19,417,883.00ConstructionRoadwayUnassignedUnassigned01/01/30-365-1 yearUnassigned → Construction / Roadway
0002-02-064El Paso11/01/28$19,632,293.75ConstructionRoadwayConstructionRoadway11/02/273651 year$(727,121.99)-4%
0109-07-056Lufkin11/01/28$1,496,424.29ConstructionRoadwayUnassignedUnassigned11/01/29-365-1 yearUnassigned → Construction / Roadway
0074-12-006Corpus Christi10/04/28$115,828.00ConstructionRoadwayConstructionRoadway10/05/273651 year
0087-04-043Corpus Christi10/04/28$197,663.00ConstructionRoadwayConstructionRoadway10/05/273651 year
0255-02-064Corpus Christi10/04/28$770,676.00ConstructionRoadwayConstructionRoadway10/05/273651 year
0507-02-061Corpus Christi10/04/28$264,978.00ConstructionRoadwayConstructionRoadway10/05/273651 year
2521-01-018Corpus Christi10/04/28$214,534.00ConstructionRoadwayConstructionRoadway10/05/273651 year
0172-06-109Fort Worth02/15/28$310,000.00ConstructionLocal LetConstructionLocal Let02/15/273651 year
0017-08-117Laredo02/02/28$8,699,053.65ConstructionRoadwayConstructionRoadway02/01/29-365-1 year$(2,344,163.85)-21%
0038-01-104Laredo02/02/28$2,615,401.95ConstructionRoadwayConstructionRoadway02/01/29-365-1 year$11,200.520.4%
0542-02-046Laredo02/02/28$6,049,963.50ConstructionRoadwayConstructionRoadway02/01/29-365-1 year$(750,036.50)-11%
0005-05-115Abilene12/01/27$769,821.00ConstructionRoadwayConstructionRoadway12/01/263651 year
0006-06-116Abilene12/01/27$404,000.00ConstructionRoadwayConstructionRoadway12/01/263651 year
0134-04-038Fort Worth12/01/27$25,848,256.43ConstructionRoadwayConstructionRoadway12/01/263651 year
0480-03-048Abilene12/01/27$111,474.00ConstructionRoadwayConstructionRoadway12/01/263651 year
1099-03-015Tyler12/01/27$427,539.09ConstructionRoadwayConstructionRoadway12/01/263651 year
1463-02-017Paris11/02/27$143,672.32ConstructionRoadwayConstructionRoadway11/01/28-365-1 year
0101-03-128Corpus Christi10/05/27$152,817.00ConstructionRoadwayConstructionRoadway10/04/28-365-1 year
1310-01-051Dallas10/05/27$8,305,445.16ConstructionRoadwayConstructionRoadway10/04/28-365-1 year$(2,369,843.23)-22%
1655-01-036Abilene07/01/27$5,512,640.10ConstructionRoadwayConstructionRoadway07/01/263651 year
0389-11-061Houston02/02/27$3,424,252.00ConstructionRoadwayConstructionRoadway02/02/28-365-1 year$(670,780.00)-16%
0008-03-140Fort Worth08/01/29$4,110,095.04ConstructionRoadwayConstructionRoadway08/02/2836412 months$734,341.3122%
0598-02-136Houston11/02/27$1,341,371.02ConstructionRoadwayConstructionRoadway11/03/2636412 months
0017-09-102San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0017-09-103San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0073-03-065San Antonio09/03/27$70,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0915-12-599San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0915-12-600San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0915-12-606San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0915-12-607San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0915-17-082San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0915-46-055San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0915-46-056San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
1273-01-040San Antonio09/03/27$300,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
1433-02-049San Antonio09/03/27$250,000.00Non-LetRail - SafetyNon-LetRail - Safety09/04/2636412 months
0220-04-049Pharr08/04/27$23,319,932.34ConstructionRoadwayConstructionRoadway08/05/2636412 months
0872-04-035Pharr08/04/27$314,622.34ConstructionRoadwayConstructionRoadway08/05/2636412 months
0714-01-016Fort Worth11/03/26$189,398.00ConstructionRoadwayConstructionRoadway11/02/27-364-12 months
0714-02-022Brownwood11/03/26$445,147.00ConstructionRoadwayConstructionRoadway11/02/27-364-12 months
1051-01-065Dallas10/01/29$105,284.34ConstructionRoadway10/04/2836212 months$(14,680.63)-12%
2461-01-011Dallas10/01/29$1,051,197.00ConstructionRoadway10/04/2836212 months$(210,599.16)-17%
0164-03-058Tyler01/01/29$8,130,000.00ConstructionRoadwayConstructionRoadway01/05/2836212 months
1986-01-075Houston01/05/28$10,245,762.00ConstructionRoadwayConstructionRoadway01/01/29-362-12 months
1259-01-051Houston04/01/29$6,060,069.00ConstructionRoadwayConstructionRoadway04/05/2836112 months
1763-02-034Tyler07/01/29$1,637,000.00ConstructionRoadwayConstructionRoadway07/06/2836012 months
1763-03-049Tyler07/01/29$4,200,000.00ConstructionRoadwayConstructionRoadway07/06/2836012 months
0022-04-021Laredo03/01/29$10,763,000.85ConstructionRoadwayConstructionRoadway03/07/2835912 months$(259,864.50)-2%
0299-13-035Laredo03/01/29$1,789,754.40ConstructionRoadwayConstructionRoadway03/07/2835912 months$235,065.6015%
0299-14-037Laredo03/01/29$1,151,274.60ConstructionRoadwayConstructionRoadway03/07/2835912 months$(713,358.45)-38%
0172-11-016Dallas03/07/28$10,429,429.46ConstructionRoadwayConstructionRoadway03/01/29-359-12 months
3138-01-039Bryan05/03/28$761,876.00ConstructionRoadwayConstructionRoadway06/01/2733711 months$(76,995.00)-9%
1558-03-114Corpus Christi12/05/28$18,000,000.00ConstructionRoadwayConstructionRoadway01/05/2833511 months$5,600,000.0045%
0926-05-009Lufkin09/01/29$9,169,916.07ConstructionRoadway10/04/2833211 months
0161-01-033Laredo02/01/29$1,438,067.40ConstructionRoadwayConstructionRoadway03/07/2833111 months$(1,496,579.45)-51%
1685-01-123Houston05/05/27$3,451,656.00ConstructionRoadwayConstructionRoadway03/07/28-307-10 months
1685-02-053Houston05/05/27$3,763,259.00ConstructionRoadwayConstructionRoadway03/07/28-307-10 months
0044-04-066Wichita Falls08/02/28$2,464,352.00ConstructionRoadwayConstructionRoadway10/05/2730210 months
0914-04-370Austin08/04/27$78,014.05ConstructionRoadwayConstructionRoadway10/06/2630210 months
0914-04-371Austin08/04/27$131,936.30ConstructionNon RoadwayConstructionNon Roadway10/06/2630210 months
0173-04-059Dallas08/05/26$6,640,524.42ConstructionRoadwayConstructionRoadway06/01/27-300-10 months
0581-01-177Dallas08/05/26$1,376,754.86ConstructionRoadwayConstructionRoadway06/01/27-300-10 months$(218,877.45)-14%
0581-01-179Dallas08/05/26$1,725,917.34ConstructionRoadwayConstructionRoadway06/01/27-300-10 months$77,435.805%
0054-06-113Brownwood07/01/26$2,329,284.20ConstructionRoadwayConstructionRoadway04/06/27-279-9 months$329,284.2016%
0902-90-374Fort Worth10/04/27$32,884,620.00ConstructionLocal LetConstructionLocal Let01/02/272759 months
2744-01-041Houston08/04/27$10,000,000.00ConstructionRoadwayConstructionRoadway11/03/262749 months
0256-01-061Wichita Falls05/05/27$200,000.00ConstructionBridgeConstructionBridge09/02/262458 months
1556-01-032Corpus Christi11/02/27$8,000,000.00ConstructionRoadwayConstructionRoadway03/03/272448 months$4,000,000.00100%
1052-02-103Corpus Christi12/05/28$293,307.00ConstructionRoadwayConstructionRoadway08/01/29-239-8 months
0853-02-033San Antonio04/06/27$16,290,622.00ConstructionRoadwayConstructionRoadway09/02/262167 months
0019-01-153Fort Worth07/01/26$1,566,691.63ConstructionRoadwayConstructionRoadway02/02/27-216-7 months$1,650.100.1%
0249-01-053Wichita Falls07/01/26$425,058.58ConstructionBridgeConstructionBridge02/02/27-216-7 months$98,563.5830%
0249-01-054Wichita Falls07/01/26$181,321.60ConstructionBridgeConstructionBridge02/02/27-216-7 months$35,167.6024%
0249-01-055Wichita Falls07/01/26$219,131.60ConstructionBridgeConstructionBridge02/02/27-216-7 months$35,442.6019%
0249-01-056Wichita Falls07/01/26$251,218.60ConstructionBridgeConstructionBridge02/02/27-216-7 months$59,002.6031%
0249-01-057Wichita Falls07/01/26$216,315.60ConstructionBridgeConstructionBridge02/02/27-216-7 months$11,982.606%
0249-01-058Wichita Falls07/01/26$166,226.60ConstructionBridgeConstructionBridge02/02/27-216-7 months$(23,121.40)-12%
0249-01-059Wichita Falls07/01/26$341,741.20ConstructionBridgeConstructionBridge02/02/27-216-7 months$139,088.2069%
0249-01-060Wichita Falls07/01/26$261,344.20ConstructionBridgeConstructionBridge02/02/27-216-7 months$(2,987.80)-1%
0259-05-086Fort Worth07/01/26$568,444.50ConstructionRoadwayConstructionRoadway02/02/27-216-7 months$2,750.000.5%
0700-04-055Austin07/01/26$66,708.00ConstructionBridgeConstructionBridge02/02/27-216-7 months
0700-04-057Austin07/01/26$68,543.50ConstructionBridgeConstructionBridge02/02/27-216-7 months
0700-04-058Austin07/01/26$657,212.50ConstructionBridgeConstructionBridge02/02/27-216-7 months
2024-01-009Corpus Christi01/01/29$886,012.00ConstructionRoadwayConstructionRoadway08/01/29-212-7 months
0912-73-249Houston04/15/27$3,022,870.19ConstructionLocal LetConstructionLocal Let09/15/262127 months
2370-01-009Odessa07/01/26$6,906,220.22ConstructionRoadwayConstructionRoadway01/06/27-189-6 months$(5,293,779.78)-43%
3330-01-011Waco11/03/26$411,155.00ConstructionRoadwayConstructionRoadway05/05/27-183-6 months
1068-01-242Fort Worth02/02/28$3,053,262.00ConstructionRoadwayConstructionRoadway08/02/28-182-6 months
0002-14-048El Paso04/02/27$11,667,327.88ConstructionLocal LetConstructionLocal Let10/02/261826 months
0915-12-691San Antonio03/03/27$250,000.00ConstructionRail - SafetyConstructionRail - Safety09/02/261826 months
3441-01-005Corpus Christi02/01/29$1,026,657.00ConstructionRoadwayConstructionRoadway08/01/29-181-6 months
0363-03-060Fort Worth09/30/26$136,306,104.60Alternative DeliveryDesign Build Finance Operate MaintainAlternative DeliveryDesign Build Finance Operate Maintain04/03/261806 months
0259-05-083Fort Worth02/02/28$8,009,664.43ConstructionRoadwayUnassignedUnassigned09/01/271545 monthsUnassigned → Construction / Roadway
0924-06-691El Paso05/01/27$3,716,750.00ConstructionLocal LetConstructionLocal Let10/02/27-154-5 months
1197-01-027Austin08/05/26$3,080,501.38ConstructionRoadwayConstructionRoadway01/06/27-154-5 months$(30,328.22)-1.0%
0015-13-437Austin02/02/27$387,000,000.00ConstructionRoadwayConstructionRoadway09/02/261535 months
0026-02-040Yoakum02/02/27$275,000.00ConstructionRoadwayConstructionRoadway09/02/261535 months
0446-03-053Yoakum02/02/27$450,000.00ConstructionRoadwayConstructionRoadway09/02/261535 months
0015-13-461Austin02/01/27$9,400,000.00Non-LetNon RoadwayNon-LetNon Roadway09/01/261535 months
0013-10-098Fort Worth07/01/26$8,676,166.77ConstructionRoadwayConstructionRoadway12/01/26-153-5 months$260,080.063%
2452-03-128San Antonio07/01/26$180,125,212.86ConstructionRoadwayConstructionRoadway12/01/26-153-5 months$(10,189,109.14)-5%
0338-02-045Houston09/06/28$822,392.23ConstructionRoadwayConstructionRoadway02/01/29-148-5 months
0338-02-046Houston09/06/28$508,316.46ConstructionRoadwayConstructionRoadway02/01/29-148-5 months
0338-03-102Houston09/06/28$313,461.82ConstructionRoadwayConstructionRoadway02/01/29-148-5 months
0720-02-095Houston09/06/28$1,000,000.00ConstructionRoadwayConstructionRoadway02/01/29-148-5 months$(15,300,278.00)-94%
1039-04-011Brownwood06/01/28$6,400,000.00ConstructionBridgeConstructionBridge01/05/281485 months
0389-05-134Houston01/06/27$4,892,062.00ConstructionNon RoadwayConstructionNon Roadway09/02/261264 months
0015-13-432Austin11/03/26$254,000,000.00ConstructionBridgeConstructionBridge07/01/261254 months
0015-13-441Austin11/03/26$85,000,000.00ConstructionRoadwayConstructionRoadway07/01/261254 months
0114-01-070Austin11/03/26$620,000.00ConstructionNon RoadwayConstructionNon Roadway07/01/261254 months
0114-01-071Austin11/03/26$4,200,000.00ConstructionNon RoadwayConstructionNon Roadway07/01/261254 months
0054-07-086Brownwood05/01/29$25,000,000.00ConstructionRoadwayConstructionRoadway01/01/291204 months
0015-13-452Austin02/02/27$40,384,615.38ConstructionRoadwayConstructionRoadway10/06/261194 months
0009-13-166Paris05/06/26$173,300,000.00Non-LetRoadwayNon-LetRoadway09/01/26-118-4 months
0471-05-051Austin12/05/28$518,770.79ConstructionRoadwayConstructionRoadway04/01/29-117-4 months
0918-47-520Dallas04/17/26$30,000,000.00Non-LetRoadwayNon-LetRoadway08/02/26-107-4 months
0053-08-077Abilene07/01/26$857,598.00ConstructionRoadwayConstructionRoadway10/06/26-97-3 months$(130,426.00)-13%
0053-09-082Abilene07/01/26$174,438.00ConstructionRoadwayConstructionRoadway10/06/26-97-3 months$(85,068.00)-33%
0068-01-073Lubbock07/01/26$138,352,841.20ConstructionRoadwayConstructionRoadway10/06/26-97-3 months$2,504,958.202%
1502-01-031Lubbock07/01/26$166,952,606.35ConstructionRoadwayConstructionRoadway10/06/26-97-3 months$2,085,314.751%
0693-03-046Abilene11/02/27$13,700,000.00ConstructionRoadwayConstructionRoadway02/02/28-92-3 months
0172-12-007Dallas05/05/27$51,472,754.02ConstructionRoadwayConstructionRoadway02/02/27923 months
1012-03-027Dallas12/01/26$8,673,294.25ConstructionRoadwayConstructionRoadway03/03/27-92-3 months$(433,664.71)-5%
1012-03-028Dallas12/01/26$6,373,822.30ConstructionRoadwayConstructionRoadway03/03/27-92-3 months$(318,691.12)-5%
1492-01-013Dallas12/01/26$1,331,491.45ConstructionRoadwayConstructionRoadway03/03/27-92-3 months$(66,574.57)-5%
0251-03-022Waco08/02/28$11,407,407.41ConstructionRoadwayConstructionRoadway05/03/28913 months
0251-04-023Brownwood08/02/28$111,585,185.19ConstructionRoadwayConstructionRoadway05/03/28913 months
0251-05-066Brownwood08/02/28$15,000,000.00ConstructionRoadwayConstructionRoadway05/03/28913 months
0978-02-090Houston04/05/28$180,015.00ConstructionRoadwayConstructionRoadway01/05/28913 months
0143-02-032San Antonio12/01/27$1,431,302.00ConstructionRoadwayConstructionRoadway09/01/27913 months
0643-01-057Bryan02/02/27$22,973,558.00ConstructionRoadwayConstructionRoadway11/03/26913 months
2635-05-005Amarillo08/05/26$47,259,223.32ConstructionRoadwayConstructionRoadway11/03/26-90-3 months
0024-06-078San Antonio04/06/27$950,000.00ConstructionRoadwayConstructionRoadway07/01/27-86-3 months
0923-09-070Brownwood08/04/27$900,000.00ConstructionBridgeConstructionBridge06/01/27642 months
0923-17-094Brownwood08/04/27$1,100,000.00ConstructionBridgeConstructionBridge06/01/27642 months
1756-01-024Yoakum08/05/26$935,446.45ConstructionRoadwayConstructionRoadway06/02/26642 months
0915-12-827San Antonio05/05/27$654,893.00ConstructionRoadwayConstructionRoadway03/03/27632 months
0915-12-828San Antonio05/05/27$362,736.00ConstructionRoadwayConstructionRoadway03/03/27632 months
0358-03-041El Paso04/06/27$690,056.73ConstructionRoadwayConstructionRoadway02/02/27632 months
0358-04-020El Paso04/06/27$101,021.15ConstructionRoadwayConstructionRoadway02/02/27632 months
0415-03-026El Paso04/06/27$58,509.62ConstructionRoadwayConstructionRoadway02/02/27632 months
0415-04-016El Paso04/06/27$39,006.73ConstructionRoadwayConstructionRoadway02/02/27632 months
0485-01-027El Paso04/06/27$158,944.23ConstructionRoadwayConstructionRoadway02/02/27632 months
0485-02-019El Paso04/06/27$105,963.46ConstructionRoadwayConstructionRoadway02/02/27632 months
0471-04-038Austin12/05/28$833,399.88ConstructionRoadwayConstructionRoadway10/04/28622 months
0807-03-041Yoakum11/02/27$479,241.00ConstructionRoadwayConstructionRoadway09/01/27622 months
0132-03-036Childress08/05/26$13,520,000.00ConstructionRoadwayConstructionRoadway10/06/26-62-2 months
0133-01-055Childress08/05/26$14,000,000.00ConstructionRoadwayConstructionRoadway10/06/26-62-2 months
0783-01-111Lubbock11/01/28$10,000,000.00ConstructionBridgeConstructionBridge01/01/29-61-2 months
0915-12-802San Antonio11/01/26$10,874,765.00ConstructionLocal LetConstructionLocal Let09/01/26612 months
0039-02-081Pharr02/01/29$1,871,711.00ConstructionRoadwayConstructionRoadway04/01/29-59-2 months
0052-07-067Lubbock12/01/27$590,724.69ConstructionRoadwayConstructionRoadway10/05/27572 months
3510-05-062Houston07/01/27$46,000,000.00ConstructionRoadwayConstructionRoadway05/05/27572 months
0976-03-120Houston10/06/26$484,617.00ConstructionRoadwayConstructionRoadway12/01/26-56-2 months
0981-01-122Houston10/06/26$1,235,700.00ConstructionRoadwayConstructionRoadway12/01/26-56-2 months
0981-02-012Houston10/06/26$678,042.00ConstructionRoadwayConstructionRoadway12/01/26-56-2 months
1414-01-024Houston10/06/26$61,492.00ConstructionRoadwayConstructionRoadway12/01/26-56-2 months
2941-02-070Houston12/01/27$51,875.00ConstructionRoadwayConstructionRoadway01/05/28-35-1 month
0079-02-059Brownwood10/06/26$240,000.00Non-LetLocalNon-LetLocal09/01/26351 month
0508-02-140Beaumont07/01/26$3,459,416.41ConstructionRoadwayConstructionRoadway08/05/26-35-1 month$(373,835.98)-10%
1421-01-027Beaumont07/01/26$1,853,387.00ConstructionRoadwayConstructionRoadway08/05/26-35-1 month$(29,957.00)-2%
1421-01-028Beaumont07/01/26$5,038,939.85ConstructionRoadwayConstructionRoadway08/05/26-35-1 month$(488,234.65)-9%
0912-37-259Houston10/15/26$13,200,000.00ConstructionLocal LetConstructionLocal Let09/15/263030 days
0022-08-027Laredo02/01/29$5,729,476.20ConstructionRoadwayConstructionRoadway03/01/29-28-28 days$(1,544,308.42)-21%
0161-03-027Laredo02/01/29$2,562,041.70ConstructionRoadwayConstructionRoadway03/01/29-28-28 days$(372,615.15)-13%
1592-01-017Laredo02/01/29$925,485.75ConstructionRoadwayConstructionRoadway03/01/29-28-28 days$(266,142.87)-22%
0028-01-109Houston08/05/26$271,016.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
0050-05-071Houston08/05/26$1,144,025.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
0050-06-106Houston08/05/26$589,346.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
0320-05-018Waco08/05/26$764,436.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
0720-02-105Houston08/05/26$153,356.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
0909-00-074Waco08/05/26$1,267,977.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
1812-01-024Houston08/05/26$1,069,424.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
3538-01-063Houston08/05/26$128,855.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
3538-01-064Houston08/05/26$67,491.00ConstructionRoadwayConstructionRoadway09/02/26-28-28 days
0348-04-052Corpus Christi01/01/29$3,500,000.00ConstructionRoadwayConstructionRoadway12/05/282727 days
0348-04-053Corpus Christi01/01/29$9,500,000.00ConstructionRoadwayConstructionRoadway12/05/282727 days
0912-00-750Houston08/15/28$500,000.00Non-LetRail - SafetyNon-LetRail - Safety08/01/281414 days
0912-00-751Houston08/15/28$600,000.00Non-LetRail - SafetyNon-LetRail - Safety08/01/281414 days
0502-01-252Houston10/15/26$600,000.00Non-LetRail - SafetyConstructionRail - Safety10/06/2699 daysConstruction / Rail - Safety → Non-Let / Rail - Safety
300 rows · download CSV

Project Type & Subtype Changes

The subtype mix within the pipeline remained mostly stable, with roadway projects constituting 75.4% of the total on May 4, 2026, up slightly from 75.3% on April 3. Notable transitions included 46 projects undergoing type or subtype changes. A primary transition observed was from unclassified to construction/roadway for 37 projects, indicating some stabilization in project classifications.

SubtypeApr 3May 4Δ (pp, n)
Roadway75.3% (4,284)75.4% (4,392)+0.1 (+108)
Bridge15.9% (905)15.5% (901)-0.4 (-4)
Local Let3.4% (195)3.4% (197)-0.0 (+2)
Non Roadway2.0% (112)2.0% (119)+0.1 (+7)
Rail - Safety1.4% (78)1.3% (78)-0.0 (+0)
CSJDistrictEst. Letting DateProject EstimateCurrent TypeCurrent SubtypeType/Subtype ΔPrev. TypePrev. SubtypePrev. CostPrev. DateLetting Δ (days)Letting Date ΔCost Δ%Cost ΔAdvertised ΔLifecycle
6501-30-001Bryan06/09/26$900,000.00MaintenanceRoutine Maintenance ContractUnassigned → Maintenance / Routine Maintenance ContractUnassignedUnassigned$900,000.0006/09/260
0364-05-043Fort Worth08/05/26$1,221,633.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,221,633.0008/05/260
0228-06-098Odessa09/02/26$691,209.02ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$691,209.0209/02/260
0014-23-042Waco10/06/26$6,000,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$10,000,000.0002/01/30-1214-3 years$(4,000,000.00)-40%
0502-01-252Houston10/15/26$600,000.00Non-LetRail - SafetyConstruction / Rail - Safety → Non-Let / Rail - SafetyConstructionRail - Safety$600,000.0010/06/2699 days
0007-06-269Brownwood11/03/26$131,061.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$131,061.0011/01/30-1459-4 years
0007-06-272Brownwood11/03/26$131,061.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$131,061.0011/01/30-1459-4 years
0271-06-141Houston11/03/26$1,300,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,300,000.0011/03/260
0271-07-359Houston11/03/26$1,300,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,300,000.0011/03/260
1007-02-020Yoakum11/03/26$662,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$662,000.0011/03/260
1685-05-144Houston11/03/26$400,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$400,000.0011/03/260
1861-01-014Amarillo11/03/26$23,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$23,000.0011/03/260
3128-01-015Waco04/01/27$992,012.50Non-LetRoadwayUnassigned → Non-Let / RoadwayUnassignedUnassigned$992,012.5004/01/270
0027-10-082Houston05/05/27$1,429,810.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,429,810.0012/01/29-941-3 years
0176-05-205Lufkin05/05/27$32,000,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1.0005/05/270$31,999,999.003199999900%
0904-11-071Amarillo05/05/27$6,100,000.00ConstructionBridgeUnassigned → Construction / BridgeUnassignedUnassigned$6,100,000.0005/05/270
1092-01-026Dallas05/05/27$12,239,522.17ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$12,239,522.1708/01/35-3010-8 years
2399-01-088Bryan05/05/27$14,661.00ConstructionLocal LetUnassigned → Construction / Local LetUnassignedUnassigned$14,661.0005/05/270
0013-08-147Fort Worth06/01/27$54,615,384.64ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$47,581,373.7601/01/30-945-3 years$7,034,010.8815%
0014-15-087Fort Worth06/01/27$20,384,615.38ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$14,558,233.8001/01/30-945-3 years$5,826,381.5840%
3510-07-022Houston07/01/27$7,574,519.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$7,574,519.0007/01/270
0245-05-054Tyler08/04/27$1,600,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,600,000.0008/04/270
0245-19-031Tyler08/04/27$470,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$470,000.0008/04/270
0521-05-144San Antonio09/01/27$589,100,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$589,100,000.0009/01/32-1827-5 years
6487-61-001Houston09/02/27$1,000,000.00MaintenanceRoutine Maintenance ContractUnassigned → Maintenance / Routine Maintenance ContractUnassignedUnassigned$1,000,000.0008/01/263971 year
0912-00-704Houston09/15/27$1,000,000.00ConstructionLocal LetConstruction / Rail - Safety → Construction / Local LetConstructionRail - Safety$1,000,000.0009/02/263781 year
0007-03-099Brownwood11/02/27$587,822.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$587,822.0011/01/34-2556-7 years
0007-03-100Brownwood11/02/27$590,391.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$590,391.0011/01/34-2556-7 years
0109-08-052Lufkin11/02/27$1,126,844.19ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,126,844.1911/01/29-730-2 years
0248-03-024Atlanta11/02/27$13,405,864.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$13,160,923.5011/02/270$244,940.502%
0259-05-083Fort Worth02/02/28$8,009,664.43ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$8,009,664.4309/01/271545 months
2170-05-018Laredo02/02/28$2,000,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$400,000.0011/01/33-2099-6 years$1,600,000.00400%
2270-01-030Abilene05/03/28$1,666,666.67ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$2,232,143.0005/01/32-1459-4 years$(565,476.33)-25%
0520-05-054Atlanta08/02/28$3,500,000.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$17,500,000.0001/01/35-2343-6 years$(14,000,000.00)-80%
0891-01-017Tyler08/02/28$1,586,530.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,586,530.0008/02/280
0273-04-051Austin09/02/28$557,981.88ConstructionLocal LetUnassigned → Construction / Local LetUnassignedUnassigned$557,981.8809/02/280
0143-14-006San Antonio09/06/28$6,540,250.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$6,540,250.0001/01/35-2308-6 years
0912-72-812Houston09/15/28$500,000.00Non-LetRailConstruction / Rail - Safety → Non-Let / RailConstructionRail - Safety$500,000.0012/01/266542 years
2664-01-007Lufkin10/04/28$4,882,572.05ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$4,882,572.0509/01/45-6176-17 years
0054-04-119Brownwood11/01/28$454,880.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$454,880.0011/01/32-1461-4 years
0070-06-053Brownwood11/01/28$263,697.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$263,697.0011/01/32-1461-4 years
0109-07-056Lufkin11/01/28$1,496,424.29ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,496,424.2911/01/29-365-1 year
0003-03-055El Paso01/01/29$12,708,817.86ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$12,708,817.8601/01/290
0192-04-110Houston01/01/29$19,417,883.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$19,417,883.0001/01/30-365-1 year
0068-02-050Lubbock02/01/29$1,371,261.60ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$1,371,261.6002/01/30-365-1 year
0843-06-020Atlanta02/01/29$3,751,667.00ConstructionRoadwayUnassigned → Construction / RoadwayUnassignedUnassigned$3,751,667.0001/01/32-1064-3 years
46 rows · download CSV

Cost Changes

The total pipeline value increased by $163.98 million to $6.71 billion. Cost changes observed include 256 projects with cost movements of 10% or more, 109 project costs increased while 147 decreased. Notably, construction projects saw a price increase of $121.78 million, highlighting areas of repricing within existing projects rather than a complete overhaul of the pipeline.

CSJDistrictEst. Letting DateProject EstimateCurrent TypeCurrent SubtypePrev. TypePrev. SubtypePrev. CostCost Δ%Cost ΔLetting Δ (days)Letting Date ΔType/Subtype ΔAdvertised ΔLifecycle
0176-05-205Lufkin05/05/27$32,000,000.00ConstructionRoadwayUnassignedUnassigned$1.00$31,999,999.003199999900%0Unassigned → Construction / Roadway
0057-03-052Bryan07/01/26$207,229.26ConstructionRoadwayConstructionRoadway$9,900.00$197,329.261993%0
2552-01-062El Paso11/02/27$11,971,606.48ConstructionRoadwayConstructionRoadway$961,538.46$11,010,068.021145%0
0276-09-011Laredo03/01/29$1,921,342.50ConstructionRoadwayConstructionRoadway$206,526.60$1,714,815.90830%0
0815-03-016Dallas10/01/30$605,163.96ConstructionRoadway$68,850.00$536,313.96779%7272 years
1316-01-068Bryan08/04/27$11,000,000.00ConstructionRoadwayConstructionRoadway$1,500,000.00$9,500,000.00633%0
0918-47-525Dallas08/02/27$8,000,000.00ConstructionRoadwayConstructionRoadway$1,111,111.11$6,888,888.89620%0
2170-05-018Laredo02/02/28$2,000,000.00ConstructionRoadwayUnassignedUnassigned$400,000.00$1,600,000.00400%-2099-6 yearsUnassigned → Construction / Roadway
0117-01-062Bryan07/01/26$266,997.40ConstructionRoadwayConstructionRoadway$77,350.00$189,647.40245%0
0683-07-013Austin01/06/27$8,173,076.92ConstructionRoadwayConstructionRoadway$2,482,355.77$5,690,721.15229%0
0081-16-004Paris07/01/26$272,653.65ConstructionNon RoadwayConstructionNon Roadway$90,000.00$182,653.65203%0
1229-02-019Laredo06/01/28$3,000,000.00ConstructionRoadwayConstructionRoadway$1,000,000.00$2,000,000.00200%0
1895-03-027Atlanta05/03/28$5,690,799.64ConstructionRoadwayConstructionRoadway$1,967,575.00$3,723,224.64189%0
0508-01-409Houston04/06/27$7,000,000.00ConstructionRoadwayConstructionRoadway$2,497,189.00$4,502,811.00180%0
0081-10-057Paris07/01/26$287,785.64ConstructionNon RoadwayConstructionNon Roadway$110,000.00$177,785.64162%0
0440-05-016Austin06/01/27$38,461,538.46ConstructionRoadwayConstructionRoadway$15,120,913.46$23,340,625.00154%0
1148-02-021Bryan07/01/26$328,623.76ConstructionRoadwayConstructionRoadway$130,514.00$198,109.76152%0
0186-03-073Bryan07/01/26$110,385.01ConstructionRoadwayConstructionRoadway$43,920.00$66,465.01151%0
0413-05-039Bryan07/01/26$525,448.20ConstructionRoadwayConstructionRoadway$209,369.00$316,079.20151%0
0907-00-239San Angelo08/05/26$497,748.40ConstructionRoadwayConstructionRoadway$199,305.00$298,443.40150%0
0677-02-017Abilene12/01/26$295,967.00ConstructionRoadwayConstructionRoadway$120,071.00$175,896.00146%0
1971-01-017Bryan07/01/26$272,226.93ConstructionRoadwayConstructionRoadway$113,474.00$158,752.93140%0
0262-06-036Bryan07/01/26$535,183.90ConstructionRoadwayConstructionRoadway$230,595.00$304,588.90132%0
3455-01-011Abilene12/01/26$447,277.00ConstructionRoadwayConstructionRoadway$208,736.00$238,541.00114%0
0683-06-035Austin01/06/27$6,346,153.85ConstructionRoadwayConstructionRoadway$3,033,990.38$3,312,163.47109%0
1210-02-016Bryan07/01/26$740,760.00ConstructionBridgeConstructionBridge$354,261.00$386,499.00109%0
0117-09-006Bryan07/01/26$26,530.90ConstructionRoadwayConstructionRoadway$12,980.00$13,550.90104%0
0022-03-032Odessa11/03/26$1,065,488.54ConstructionBridgeConstructionBridge$530,410.80$535,077.74101%0
1556-01-032Corpus Christi11/02/27$8,000,000.00ConstructionRoadwayConstructionRoadway$4,000,000.00$4,000,000.00100%2448 months
0912-37-265Houston05/15/26$1.00ConstructionLocal LetConstructionLocal Let$9,413,000.00$(9,412,999.00)-100%0
0005-08-107Abilene12/01/26$1,058,935.00ConstructionRoadwayConstructionRoadway$535,593.00$523,342.0098%0
1003-01-098Houston09/01/31$1,088,146.00ConstructionRoadway$24,146,123.00$(23,057,977.00)-95%10903 years
0720-02-095Houston09/06/28$1,000,000.00ConstructionRoadwayConstructionRoadway$16,300,278.00$(15,300,278.00)-94%-148-5 months
0091-06-061Dallas07/01/26$5,190,264.90ConstructionRoadwayConstructionRoadway$2,734,376.72$2,455,888.1890%0
1555-01-009Corpus Christi07/01/26$15,605.17ConstructionRoadwayConstructionRoadway$139,502.00$(123,896.83)-89%0
0005-06-124Abilene12/01/26$1,624,233.00ConstructionRoadwayConstructionRoadway$864,449.00$759,784.0088%0
3116-01-033Corpus Christi07/01/26$25,616.10ConstructionRoadwayConstructionRoadway$151,985.00$(126,368.90)-83%0
0907-00-240San Angelo08/05/26$49,251.00ConstructionRoadwayConstructionRoadway$273,105.00$(223,854.00)-82%0
0092-05-058Dallas10/06/26$4,553,198.71ConstructionRoadwayConstructionRoadway$25,202,541.30$(20,649,342.59)-82%0
0520-05-054Atlanta08/02/28$3,500,000.00ConstructionRoadwayUnassignedUnassigned$17,500,000.00$(14,000,000.00)-80%-2343-6 yearsUnassigned → Construction / Roadway
0675-02-101Bryan07/01/26$1,074.76ConstructionRoadwayConstructionRoadway$5,190.00$(4,115.24)-79%0
0114-02-112Austin08/05/26$615,753.25ConstructionRoadwayConstructionRoadway$2,735,940.00$(2,120,186.75)-77%0
1115-01-010Corpus Christi07/01/26$132,013.59ConstructionRoadwayConstructionRoadway$583,647.00$(451,633.41)-77%0
0296-06-016Abilene12/01/26$128,965.00ConstructionRoadwayConstructionRoadway$72,764.00$56,201.0077%0
0921-26-113Pharr09/03/27$4,200,000.00ConstructionLocal LetConstructionLocal Let$18,000,000.00$(13,800,000.00)-77%0
1294-02-022Corpus Christi07/01/26$173,642.98ConstructionRoadwayConstructionRoadway$723,570.00$(549,927.02)-76%0
0140-05-029Odessa11/03/26$127,785.00ConstructionBridgeConstructionBridge$522,571.68$(394,786.68)-76%0
0332-02-028Abilene12/01/26$123,275.00ConstructionRoadwayConstructionRoadway$70,662.00$52,613.0074%0
0367-02-084Houston09/01/31$500,000.00ConstructionRoadway$1,906,590.00$(1,406,590.00)-74%12733 years
3089-01-013Dallas07/01/26$726,590.00ConstructionRoadwayConstructionRoadway$419,957.48$306,632.5273%0
0371-05-022Corpus Christi07/01/26$88,823.89ConstructionRoadwayConstructionRoadway$314,636.00$(225,812.11)-72%0
0058-04-023Tyler12/01/26$582,678.84ConstructionRoadwayConstructionRoadway$341,403.96$241,274.8871%0
0140-01-083Odessa11/03/26$159,563.00ConstructionBridgeConstructionBridge$536,429.33$(376,866.33)-70%0
0249-01-059Wichita Falls07/01/26$341,741.20ConstructionBridgeConstructionBridge$202,653.00$139,088.2069%-216-7 months
1446-01-016Corpus Christi07/01/26$41,470.22ConstructionRoadwayConstructionRoadway$130,740.00$(89,269.78)-68%0
0791-01-021Amarillo11/02/27$450,730.00ConstructionRoadwayConstructionRoadway$1,363,000.00$(912,270.00)-67%0
0271-14-244Houston02/02/28$1,000,000.00ConstructionRoadwayConstructionRoadway$3,000,000.00$(2,000,000.00)-67%0
2942-02-019Corpus Christi07/01/26$100,233.75ConstructionRoadwayConstructionRoadway$285,222.00$(184,988.25)-65%0
0204-05-046Bryan07/01/26$103,360.42ConstructionRoadwayConstructionRoadway$64,590.00$38,770.4260%0
0677-01-024Abilene12/01/26$429,303.00ConstructionRoadwayConstructionRoadway$271,073.00$158,230.0058%0
0140-04-049Odessa11/03/26$230,220.00ConstructionBridgeConstructionBridge$539,414.40$(309,194.40)-57%0
0521-06-175San Antonio08/05/26$2,670,328.38ConstructionRoadwayConstructionRoadway$6,184,458.00$(3,514,129.62)-57%0
1809-01-023Bryan07/01/26$862.92ConstructionRoadwayConstructionRoadway$1,990.00$(1,127.08)-57%0
1147-01-034Bryan07/01/26$80,027.00ConstructionRoadwayConstructionRoadway$51,110.00$28,917.0057%0
0915-12-829San Antonio09/06/28$2,435,670.00ConstructionRoadwayConstructionRoadway$1,566,606.00$869,064.0055%0
0980-02-020Houston09/01/27$10,000,000.00ConstructionRoadwayConstructionRoadway$21,668,136.00$(11,668,136.00)-54%0
0166-05-009Bryan07/01/26$2,881.00ConstructionRoadwayConstructionRoadway$6,160.00$(3,279.00)-53%0
0520-09-057Tyler07/01/26$84,542.50ConstructionRoadwayConstructionRoadway$180,000.00$(95,457.50)-53%0
0047-03-106Paris08/05/26$1,164,466.93ConstructionRoadwayConstructionRoadway$2,463,364.40$(1,298,897.47)-53%0
1392-03-017Dallas07/01/26$3,043,980.80ConstructionRoadwayConstructionRoadway$2,006,803.41$1,037,177.3952%0
0161-01-033Laredo02/01/29$1,438,067.40ConstructionRoadwayConstructionRoadway$2,934,646.85$(1,496,579.45)-51%33111 months
0598-03-062Houston02/02/27$4,600,000.00ConstructionRoadwayConstructionRoadway$9,268,723.98$(4,668,723.98)-50%0
0315-10-013Bryan07/01/26$777.00ConstructionRoadwayConstructionRoadway$1,560.00$(783.00)-50%0
0254-01-149Corpus Christi07/01/27$15,000,000.00ConstructionRoadwayConstructionRoadway$10,000,000.00$5,000,000.0050%0
0598-04-030Houston02/02/27$4,200,000.00ConstructionRoadwayConstructionRoadway$8,370,328.77$(4,170,328.77)-50%0
0921-06-330Pharr09/03/27$25,435,821.86ConstructionLocal LetConstructionLocal Let$17,023,422.00$8,412,399.8649%0
0047-04-041Dallas06/01/27$1,749,097.74ConstructionRoadwayConstructionRoadway$1,178,505.94$570,591.8048%0
0205-01-052Bryan07/01/26$167,380.00ConstructionBridgeConstructionBridge$112,900.00$54,480.0048%0
0517-02-046San Antonio09/01/27$6,501,914.80ConstructionBridgeConstructionBridge$12,500,000.00$(5,998,085.20)-48%0
1223-03-015Bryan07/01/26$34,452.05ConstructionRoadwayConstructionRoadway$65,230.00$(30,777.95)-47%0
1062-03-055Houston01/05/28$7,000,000.00ConstructionRoadwayConstructionRoadway$13,000,000.00$(6,000,000.00)-46%0
0172-09-047Fort Worth09/02/26$4,029,170.17ConstructionRoadwayConstructionRoadway$7,466,647.62$(3,437,477.45)-46%0
0587-01-070Houston07/06/28$4,391,550.00ConstructionNon RoadwayConstructionNon Roadway$8,058,425.93$(3,666,875.93)-46%0
1558-03-114Corpus Christi12/05/28$18,000,000.00ConstructionRoadwayConstructionRoadway$12,400,000.00$5,600,000.0045%33511 months
0107-02-041Abilene12/01/26$860,160.00ConstructionRoadwayConstructionRoadway$593,609.00$266,551.0045%0
0441-07-079Odessa11/03/26$848,068.00ConstructionBridgeConstructionBridge$588,806.40$259,261.6044%0
2370-01-009Odessa07/01/26$6,906,220.22ConstructionRoadwayConstructionRoadway$12,200,000.00$(5,293,779.78)-43%-189-6 months
0668-03-010Abilene12/01/26$195,558.00ConstructionRoadwayConstructionRoadway$136,591.00$58,967.0043%0
0263-05-025Abilene12/01/26$1,173,898.00ConstructionRoadwayConstructionRoadway$820,585.00$353,313.0043%0
0074-04-049Corpus Christi01/01/30$3,000,000.00ConstructionRoadway$2,100,000.00$900,000.0043%7272 years
0919-02-043Atlanta07/01/26$51,552.00ConstructionRoadwayConstructionRoadway$90,000.00$(38,448.00)-43%0
2170-05-017Laredo08/04/27$10,000,000.00ConstructionRoadwayConstructionRoadway$17,247,810.98$(7,247,810.98)-42%0
1194-02-020Beaumont07/01/26$5,913,739.66ConstructionRoadwayConstructionRoadway$10,174,500.00$(4,260,760.34)-42%0
0187-05-062Houston05/06/26$3,421,687.50ConstructionRoadwayConstructionRoadway$5,871,532.50$(2,449,845.00)-42%0
0074-05-105Corpus Christi01/05/28$12,000,000.00ConstructionRoadwayConstructionRoadway$8,500,000.00$3,500,000.0041%0
0057-04-035Bryan07/01/26$9,072.53ConstructionRoadwayConstructionRoadway$15,310.00$(6,237.47)-41%0
0088-02-063Corpus Christi07/01/26$2,442,845.67ConstructionRoadwayConstructionRoadway$4,100,000.00$(1,657,154.33)-40%0
0092-14-109Dallas08/04/27$11,646,900.00ConstructionRoadwayConstructionRoadway$8,308,500.00$3,338,400.0040%0
0014-15-087Fort Worth06/01/27$20,384,615.38ConstructionRoadwayUnassignedUnassigned$14,558,233.80$5,826,381.5840%-945-3 yearsUnassigned → Construction / Roadway
2150-04-100Laredo02/02/28$7,165,023.60ConstructionRoadwayConstructionRoadway$11,942,000.00$(4,776,976.40)-40%0
0014-23-041Waco10/06/26$6,000,000.00ConstructionRoadwayConstructionRoadway$10,000,000.00$(4,000,000.00)-40%0
0014-23-042Waco10/06/26$6,000,000.00ConstructionRoadwayUnassignedUnassigned$10,000,000.00$(4,000,000.00)-40%-1214-3 yearsUnassigned → Construction / Roadway
0718-02-079Fort Worth07/01/26$353,033.50ConstructionRoadwayConstructionRoadway$578,334.00$(225,300.50)-39%0
2374-04-100Dallas08/02/26$582,613.56ConstructionRoadwayConstructionRoadway$420,000.00$162,613.5639%0
0093-03-027Bryan07/01/26$25,432.11ConstructionRoadwayConstructionRoadway$41,340.00$(15,907.89)-38%0
0299-14-037Laredo03/01/29$1,151,274.60ConstructionRoadwayConstructionRoadway$1,864,633.05$(713,358.45)-38%35912 months
2270-01-029Abilene07/01/26$319,006.50ConstructionRoadwayConstructionRoadway$515,464.00$(196,457.50)-38%0
0114-09-103Bryan07/01/26$224,868.34ConstructionRoadwayConstructionRoadway$163,870.00$60,998.3437%0
0089-09-090Houston06/02/26$1,152,912.75ConstructionRoadwayConstructionRoadway$842,339.39$310,573.3637%0
0140-05-028Odessa11/03/26$886,246.00ConstructionBridgeConstructionBridge$650,262.99$235,983.0136%0
0383-04-065Corpus Christi07/01/30$3,000,000.00ConstructionRoadway$4,600,000.00$(1,600,000.00)-35%5461 year
0088-03-050Corpus Christi07/01/26$328,564.34ConstructionRoadwayConstructionRoadway$500,000.00$(171,435.66)-34%0
0028-04-084Beaumont07/01/26$2,109,576.76ConstructionRoadwayConstructionRoadway$3,200,000.00$(1,090,423.24)-34%0
0370-05-057Yoakum07/01/26$722,928.50ConstructionRoadwayConstructionRoadway$540,000.00$182,928.5034%0
0092-14-107Dallas07/01/26$90,688.50ConstructionRoadwayConstructionRoadway$136,800.30$(46,111.80)-34%0
1020-01-068Atlanta03/03/27$2,400,000.00ConstructionRoadwayConstructionRoadway$1,801,730.00$598,270.0033%-456-1 year
0027-06-062Houston06/02/26$484,375.15ConstructionRoadwayConstructionRoadway$364,239.94$120,135.2133%0
0053-09-082Abilene07/01/26$174,438.00ConstructionRoadwayConstructionRoadway$259,506.00$(85,068.00)-33%-97-3 months
1529-03-010Abilene12/01/26$225,891.00ConstructionRoadwayConstructionRoadway$170,199.28$55,691.7233%0
0074-03-050Corpus Christi01/01/30$4,500,000.00ConstructionRoadway$3,400,000.00$1,100,000.0032%7272 years
0921-06-382Pharr12/05/28$1,383,277.50ConstructionBridgeConstructionBridge$1,045,956.45$337,321.0532%0
0909-40-090Waco07/01/26$360,583.67ConstructionBridgeConstructionBridge$530,000.00$(169,416.33)-32%0
0909-40-095Waco07/01/26$432,052.09ConstructionBridgeConstructionBridge$635,000.00$(202,947.91)-32%0
0914-04-367Austin07/01/26$254,757.70ConstructionRoadwayConstructionRoadway$373,363.00$(118,605.30)-32%0
0315-02-061Bryan07/01/26$18,748.81ConstructionRoadwayConstructionRoadway$27,180.00$(8,431.19)-31%0
0249-01-056Wichita Falls07/01/26$251,218.60ConstructionBridgeConstructionBridge$192,216.00$59,002.6031%-216-7 months
0249-01-053Wichita Falls07/01/26$425,058.58ConstructionBridgeConstructionBridge$326,495.00$98,563.5830%-216-7 months
0902-90-270Fort Worth07/01/26$1,096,961.55ConstructionBridgeConstructionBridge$1,570,540.54$(473,578.99)-30%0
0909-40-094Waco07/01/26$391,376.83ConstructionBridgeConstructionBridge$560,000.00$(168,623.17)-30%0
0578-03-057Bryan07/01/26$8,257.46ConstructionRoadwayConstructionRoadway$11,750.00$(3,492.54)-30%0
0057-04-036Bryan07/01/26$38,310.83ConstructionRoadwayConstructionRoadway$54,500.00$(16,189.17)-30%0
2528-01-006Odessa08/05/26$8,304,083.23ConstructionRoadwayConstructionRoadway$11,800,000.00$(3,495,916.77)-30%0
0187-05-061Houston05/06/26$3,102,767.75ConstructionRoadwayConstructionRoadway$4,378,050.25$(1,275,282.50)-29%0
0990-02-014Corpus Christi11/01/28$6,500,000.00ConstructionRoadwayConstructionRoadway$5,038,199.00$1,461,801.0029%0
0382-05-023Bryan07/01/26$31,660.42ConstructionRoadwayConstructionRoadway$44,470.00$(12,809.58)-29%0
0913-27-094Yoakum07/01/26$785,402.50ConstructionBridgeConstructionBridge$610,270.00$175,132.5029%0
0910-07-103Tyler07/01/26$64,186.00ConstructionRoadwayConstructionRoadway$90,000.00$(25,814.00)-29%0
0902-20-238Fort Worth08/05/26$793,145.80ConstructionBridgeConstructionBridge$1,109,884.81$(316,739.01)-29%0
0047-05-062Dallas06/01/27$2,545,733.42ConstructionRoadwayConstructionRoadway$1,989,602.84$556,130.5828%0
0318-02-028Abilene12/01/26$1,135,643.00ConstructionRoadwayConstructionRoadway$893,219.00$242,424.0027%0
0070-04-041San Angelo07/01/26$175,049.00ConstructionRoadwayConstructionRoadway$138,200.00$36,849.0027%-644-2 years
0921-02-440Pharr05/02/28$6,567,414.39ConstructionLocal LetConstructionLocal Let$5,196,846.00$1,370,568.3926%0
0081-03-065Dallas04/05/28$3,181,271.71ConstructionRoadwayConstructionRoadway$4,276,221.30$(1,094,949.59)-26%0
2270-01-030Abilene05/03/28$1,666,666.67ConstructionRoadwayUnassignedUnassigned$2,232,143.00$(565,476.33)-25%-1459-4 yearsUnassigned → Construction / Roadway
0921-02-532Pharr05/02/27$1,865,601.76ConstructionLocal LetConstructionLocal Let$1,490,283.00$375,318.7625%0
0291-11-023San Antonio07/01/26$32,690.93ConstructionRoadwayConstructionRoadway$26,117.13$6,573.8025%0
0186-04-036Bryan07/01/26$28,291.79ConstructionRoadwayConstructionRoadway$22,690.00$5,601.7925%0
0166-07-073Bryan06/02/26$298,878.00ConstructionBridgeConstructionBridge$240,028.00$58,850.0025%0
0686-02-033Houston02/01/29$1,508,379.00ConstructionRoadwayConstructionRoadway$1,992,603.00$(484,224.00)-24%0
0091-09-019Dallas01/01/30$8,932,684.66ConstructionRoadway$11,795,533.04$(2,862,848.38)-24%3651 year
0914-04-368Austin07/01/26$292,939.00ConstructionNon RoadwayConstructionNon Roadway$386,671.00$(93,732.00)-24%0
0909-40-079Waco07/01/26$530,503.45ConstructionBridgeConstructionBridge$700,000.00$(169,496.55)-24%0
0053-20-007Abilene12/01/26$196,776.00ConstructionRoadwayConstructionRoadway$158,589.00$38,187.0024%0
0249-01-054Wichita Falls07/01/26$181,321.60ConstructionBridgeConstructionBridge$146,154.00$35,167.6024%-216-7 months
0916-35-231Corpus Christi05/06/26$14,038,390.99ConstructionBridgeConstructionBridge$11,336,329.94$2,702,061.0524%0
0817-01-029Dallas10/05/27$335,057.72ConstructionRoadwayConstructionRoadway$270,585.00$64,472.7224%0
3610-01-004Abilene12/01/26$150,278.00ConstructionRoadwayConstructionRoadway$121,611.00$28,667.0024%0
0187-05-066Houston07/01/26$259,921.71ConstructionRoadwayConstructionRoadway$210,344.00$49,577.7124%0
0921-02-535Pharr10/05/27$846,529.43ConstructionBridgeConstructionBridge$688,235.31$158,294.1223%0
0205-02-078Bryan07/01/26$25,938.89ConstructionRoadwayConstructionRoadway$33,480.00$(7,541.11)-23%0
1592-01-017Laredo02/01/29$925,485.75ConstructionRoadwayConstructionRoadway$1,191,628.62$(266,142.87)-22%-28-28 days
1310-01-051Dallas10/05/27$8,305,445.16ConstructionRoadwayConstructionRoadway$10,675,288.39$(2,369,843.23)-22%-365-1 year
0070-03-062San Angelo07/01/26$3,599,697.00ConstructionRoadwayConstructionRoadway$4,626,157.00$(1,026,460.00)-22%-644-2 years
0150-02-043Austin08/05/26$2,532,219.03ConstructionRoadwayConstructionRoadway$3,253,437.15$(721,218.12)-22%0
0008-03-140Fort Worth08/01/29$4,110,095.04ConstructionRoadwayConstructionRoadway$3,375,753.73$734,341.3122%36412 months
0022-08-027Laredo02/01/29$5,729,476.20ConstructionRoadwayConstructionRoadway$7,273,784.62$(1,544,308.42)-21%-28-28 days
0017-08-117Laredo02/02/28$8,699,053.65ConstructionRoadwayConstructionRoadway$11,043,217.50$(2,344,163.85)-21%-365-1 year
0114-02-115Austin08/05/26$432,938.25ConstructionRoadwayConstructionRoadway$546,844.87$(113,906.62)-21%0
0912-72-846Houston06/02/26$6,892,110.25ConstructionRoadwayConstructionRoadway$5,709,769.58$1,182,340.6721%0
0315-03-073Bryan07/01/26$77,696.54ConstructionRoadwayConstructionRoadway$97,980.00$(20,283.46)-21%0
0924-06-780El Paso05/05/27$1,699,269.23ConstructionLocal LetConstructionLocal Let$2,120,687.60$(421,418.37)-20%0
0353-05-136Dallas08/02/28$4,698,537.36ConstructionRoadwayConstructionRoadway$5,840,463.89$(1,141,926.53)-20%0
0262-06-037Bryan07/01/26$90,736.00ConstructionBridgeConstructionBridge$112,636.80$(21,900.80)-19%0
0249-01-055Wichita Falls07/01/26$219,131.60ConstructionBridgeConstructionBridge$183,689.00$35,442.6019%-216-7 months
0266-05-055Yoakum07/01/26$894,213.00ConstructionRoadwayConstructionRoadway$750,000.00$144,213.0019%0
0921-02-399Pharr01/04/27$7,360,853.76ConstructionLocal LetConstructionLocal Let$9,110,000.00$(1,749,146.24)-19%0
0921-06-362Pharr05/02/28$29,953,540.52ConstructionLocal LetConstructionLocal Let$37,018,742.29$(7,065,201.77)-19%0
3022-02-009Dallas02/01/29$5,938,245.17ConstructionRoadwayConstructionRoadway$4,988,234.68$950,010.4919%7302 years
0205-03-059Bryan07/01/26$56,446.02ConstructionRoadwayConstructionRoadway$69,710.00$(13,263.98)-19%0
0440-06-030Austin01/06/27$39,074,038.46ConstructionRoadwayConstructionRoadway$48,076,923.08$(9,002,884.62)-19%0
0165-02-061Tyler07/01/26$77,883,082.55ConstructionRoadwayConstructionRoadway$66,001,500.00$11,881,582.5518%0
0921-02-396Pharr01/02/28$8,213,618.71ConstructionLocal LetConstructionLocal Let$9,987,258.04$(1,773,639.33)-18%0
0281-01-038Dallas10/06/26$1,090,833.41ConstructionRoadwayConstructionRoadway$1,323,157.58$(232,324.17)-18%0
0368-03-042Beaumont07/01/26$1,762,157.35ConstructionRoadwayConstructionRoadway$1,500,000.00$262,157.3517%-644-2 years
1052-01-085Corpus Christi06/02/26$137,533.52ConstructionRoadwayConstructionRoadway$166,276.32$(28,742.80)-17%0
2886-02-018Corpus Christi06/02/26$135,858.09ConstructionRoadwayConstructionRoadway$163,796.82$(27,938.73)-17%0
0998-04-010Bryan07/01/26$1,943.20ConstructionRoadwayConstructionRoadway$2,340.00$(396.80)-17%0
0205-01-053Bryan07/01/26$64,752.84ConstructionRoadwayConstructionRoadway$77,950.00$(13,197.16)-17%0
0291-10-117San Antonio07/01/26$3,328,257.33ConstructionRoadwayConstructionRoadway$2,846,766.70$481,490.6317%0
2461-01-011Dallas10/01/29$1,051,197.00ConstructionRoadway$1,261,796.16$(210,599.16)-17%36212 months
0166-08-064Bryan07/01/26$132,202.02ConstructionRoadwayConstructionRoadway$158,450.00$(26,247.98)-17%0
0054-06-113Brownwood07/01/26$2,329,284.20ConstructionRoadwayConstructionRoadway$2,000,000.00$329,284.2016%-279-9 months
0389-11-061Houston02/02/27$3,424,252.00ConstructionRoadwayConstructionRoadway$4,095,032.00$(670,780.00)-16%-365-1 year
0114-02-120Austin08/05/26$2,996,561.70ConstructionRoadwayConstructionRoadway$3,577,315.00$(580,753.30)-16%0
2266-02-168Fort Worth06/02/26$1,434,972.42ConstructionNon RoadwayConstructionNon Roadway$1,711,952.50$(276,980.08)-16%0
0921-06-377Pharr05/01/27$1,113,545.00ConstructionLocal LetConstructionLocal Let$1,325,118.55$(211,573.55)-16%0
0007-06-268Brownwood07/01/26$1,261,391.90ConstructionRoadwayConstructionRoadway$1,500,000.00$(238,608.10)-16%0
0199-01-091Tyler07/01/26$597,189.65ConstructionRoadwayConstructionRoadway$516,736.73$80,452.9216%0
0902-90-129Fort Worth07/01/26$2,365,443.90ConstructionBridgeConstructionBridge$2,794,310.91$(428,867.01)-15%0
0718-01-078Dallas06/01/27$457,789.20ConstructionBridgeConstructionBridge$540,000.00$(82,210.80)-15%0
0095-05-061Dallas06/01/28$17,400,554.15ConstructionRoadwayConstructionRoadway$20,518,087.04$(3,117,532.89)-15%0
0083-02-060Paris08/05/26$78,448.00ConstructionRoadwayConstructionRoadway$92,448.45$(14,000.45)-15%0
0315-01-040Bryan07/01/26$3,224.76ConstructionRoadwayConstructionRoadway$3,800.00$(575.24)-15%0
1562-03-022Bryan07/01/26$77,194.55ConstructionRoadwayConstructionRoadway$90,970.00$(13,775.45)-15%0
0299-13-035Laredo03/01/29$1,789,754.40ConstructionRoadwayConstructionRoadway$1,554,688.80$235,065.6015%35912 months
0265-03-054Austin07/01/26$745,820.25ConstructionRoadwayConstructionRoadway$877,520.25$(131,700.00)-15%0
0039-10-096Pharr12/01/27$3,579,328.00ConstructionBridgeConstructionBridge$3,112,459.28$466,868.7215%0
0013-08-147Fort Worth06/01/27$54,615,384.64ConstructionRoadwayUnassignedUnassigned$47,581,373.76$7,034,010.8815%-945-3 yearsUnassigned → Construction / Roadway
0039-12-260Pharr09/01/27$11,269,925.14ConstructionBridgeConstructionBridge$9,847,029.39$1,422,895.7514%0
1003-01-112Houston03/07/28$722,090.00ConstructionRoadwayConstructionRoadway$631,223.00$90,867.0014%0
0015-09-208Austin07/01/26$2,898,081.65ConstructionRoadwayConstructionRoadway$3,380,279.55$(482,197.90)-14%0
3510-04-066Houston07/01/26$21,704,627.94ConstructionRoadwayConstructionRoadway$18,997,823.00$2,706,804.9414%0
0920-38-287Beaumont06/02/26$2,540,906.12ConstructionBridgeConstructionBridge$2,960,906.12$(420,000.00)-14%0
2446-01-037Bryan07/01/26$25,652.54ConstructionRoadwayConstructionRoadway$22,470.00$3,182.5414%0
3510-04-065Houston07/01/26$3,386,248.00ConstructionNon RoadwayConstructionNon Roadway$3,942,056.00$(555,808.00)-14%0
0581-01-180Dallas08/02/28$6,032,797.68ConstructionRoadwayConstructionRoadway$7,010,101.85$(977,304.17)-14%0
2859-01-011Abilene12/01/26$487,839.00ConstructionRoadwayConstructionRoadway$428,430.00$59,409.0014%0
0914-04-364Austin06/02/26$516,136.30ConstructionNon RoadwayConstructionNon Roadway$598,936.45$(82,800.15)-14%0
3312-02-019Houston01/06/27$3,803,740.00ConstructionRoadwayConstructionRoadway$4,410,422.00$(606,682.00)-14%0
0581-01-177Dallas08/05/26$1,376,754.86ConstructionRoadwayConstructionRoadway$1,595,632.31$(218,877.45)-14%-300-10 months
0675-05-112Bryan07/01/26$35,202.45ConstructionRoadwayConstructionRoadway$40,780.00$(5,577.55)-14%0
1065-02-045Pharr08/04/27$1,576,228.00ConstructionRoadwayConstructionRoadway$1,824,968.00$(248,740.00)-14%0
0675-08-121Houston07/01/26$4,119,323.00ConstructionNon RoadwayConstructionNon Roadway$3,627,242.00$492,081.0014%0
0027-13-245Houston06/02/26$248,970.25ConstructionRoadwayConstructionRoadway$287,794.37$(38,824.12)-13%0
0072-12-202San Antonio09/02/26$247,586.98ConstructionRoadwayConstructionRoadway$218,366.32$29,220.6613%0
0395-01-036Bryan07/01/26$90,098.80ConstructionRoadwayConstructionRoadway$79,520.00$10,578.8013%0
0047-06-182Dallas12/03/26$1,127,591.83ConstructionLocal LetConstructionLocal Let$1,300,000.00$(172,408.17)-13%0
0053-08-077Abilene07/01/26$857,598.00ConstructionRoadwayConstructionRoadway$988,024.00$(130,426.00)-13%-97-3 months
0053-12-075Abilene12/01/26$799,989.00ConstructionRoadwayConstructionRoadway$708,053.00$91,936.0013%0
0165-03-036Tyler07/01/26$46,939,079.29ConstructionRoadwayConstructionRoadway$53,872,550.00$(6,933,470.71)-13%0
0199-01-090Tyler07/01/26$707,258.21ConstructionRoadwayConstructionRoadway$811,456.44$(104,198.23)-13%0
0919-19-093Atlanta06/02/26$897,068.40ConstructionBridgeConstructionBridge$795,421.40$101,647.0013%0
0161-03-027Laredo02/01/29$2,562,041.70ConstructionRoadwayConstructionRoadway$2,934,656.85$(372,615.15)-13%-28-28 days
0921-02-561Pharr01/02/28$1,917,438.00ConstructionNon RoadwayConstructionNon Roadway$2,191,115.00$(273,677.00)-12%0
0114-02-116Austin08/05/26$3,331,178.85ConstructionRoadwayConstructionRoadway$3,800,845.31$(469,666.46)-12%0
1051-01-065Dallas10/01/29$105,284.34ConstructionRoadway$119,964.97$(14,680.63)-12%36212 months
0249-01-058Wichita Falls07/01/26$166,226.60ConstructionBridgeConstructionBridge$189,348.00$(23,121.40)-12%-216-7 months
0446-01-056Yoakum07/01/26$1,791,665.95ConstructionRoadwayConstructionRoadway$1,600,000.00$191,665.9512%0
2011-02-016Abilene12/01/26$1,002,591.00ConstructionRoadwayConstructionRoadway$1,138,058.00$(135,467.00)-12%0
0006-16-005Abilene12/01/26$132,725.00ConstructionRoadwayConstructionRoadway$150,633.26$(17,908.26)-12%0
0114-02-111Austin08/05/26$526,301.50ConstructionRoadwayConstructionRoadway$596,316.00$(70,014.50)-12%0
1971-02-009Bryan07/01/26$4,311.80ConstructionRoadwayConstructionRoadway$4,880.00$(568.20)-12%0
1095-03-019Corpus Christi06/02/26$136,336.35ConstructionRoadwayConstructionRoadway$154,293.80$(17,957.45)-12%0
0204-09-067Bryan07/01/26$45,448.23ConstructionRoadwayConstructionRoadway$51,400.00$(5,951.77)-12%0
0720-03-154Houston06/02/26$786,744.75ConstructionRoadwayConstructionRoadway$887,926.00$(101,181.25)-11%0
0143-01-068San Antonio07/01/26$2,514,127.89ConstructionRoadwayConstructionRoadway$2,833,055.08$(318,927.19)-11%0
3417-02-039Austin07/01/26$432,477.50ConstructionNon RoadwayConstructionNon Roadway$487,340.00$(54,862.50)-11%0
0543-02-086Houston07/01/26$173,335.46ConstructionRoadwayConstructionRoadway$195,093.00$(21,757.54)-11%0
0171-04-087Fort Worth07/01/26$347,739.50ConstructionRoadwayConstructionRoadway$391,194.00$(43,454.50)-11%0
0542-02-046Laredo02/02/28$6,049,963.50ConstructionRoadwayConstructionRoadway$6,800,000.00$(750,036.50)-11%-365-1 year
1429-01-039Pharr05/06/26$266,656.05ConstructionRoadwayConstructionRoadway$241,056.05$25,600.0011%0
0006-02-126Abilene12/01/26$690,784.00ConstructionRoadwayConstructionRoadway$772,055.00$(81,271.00)-11%0
0266-04-053Yoakum07/01/26$1,798,100.25ConstructionRoadwayConstructionRoadway$2,009,165.00$(211,064.75)-11%0
2130-01-014Bryan07/01/26$59,025.95ConstructionRoadwayConstructionRoadway$65,840.00$(6,814.05)-10%0
0456-02-037Bryan07/01/26$7,492.42ConstructionRoadwayConstructionRoadway$8,340.00$(847.58)-10%0
0915-12-796San Antonio07/01/26$333,380.95ConstructionRoadwayConstructionRoadway$371,096.05$(37,715.10)-10%0
0047-07-248Dallas07/01/26$306,923.00ConstructionRoadwayConstructionRoadway$340,733.40$(33,810.40)-10%0
3110-01-003Lufkin07/01/26$4,060,440.80ConstructionRoadwayConstructionRoadway$4,505,928.36$(445,487.56)-10%0
0918-46-334Dallas06/02/26$1,510,580.00ConstructionBridgeConstructionBridge$1,675,899.60$(165,319.60)-10%0
0333-01-033Abilene12/01/26$1,647,371.00ConstructionRoadwayConstructionRoadway$1,500,000.00$147,371.0010%0
0508-02-140Beaumont07/01/26$3,459,416.41ConstructionRoadwayConstructionRoadway$3,833,252.39$(373,835.98)-10%-35-1 month
0492-04-041Tyler07/01/26$27,128,231.85ConstructionRoadwayConstructionRoadway$30,037,794.85$(2,909,563.00)-10%0
0430-01-070Dallas08/02/28$5,169,642.48ConstructionRoadwayConstructionRoadway$5,719,193.52$(549,551.04)-10%0
1718-05-021Odessa04/05/28$2,153,993.53ConstructionRoadwayConstructionRoadway$2,381,745.00$(227,751.47)-10%0
0213-03-112Lufkin07/01/26$3,331,418.00ConstructionBridgeConstructionBridge$3,682,752.30$(351,334.30)-10%0
0918-46-335Dallas06/02/26$994,466.00ConstructionBridgeConstructionBridge$1,097,504.80$(103,038.80)-9%0
3138-01-039Bryan05/03/28$761,876.00ConstructionRoadwayConstructionRoadway$838,871.00$(76,995.00)-9%33711 months
0921-02-533Pharr05/01/27$1,107,531.00ConstructionLocal LetConstructionLocal Let$1,218,284.10$(110,753.10)-9%0
0025-02-234San Antonio08/05/26$7,487,310.06ConstructionRoadwayConstructionRoadway$8,226,172.00$(738,861.94)-9%0
0110-05-136Houston05/06/26$1,080,682.20ConstructionRoadwayConstructionRoadway$991,742.20$88,940.009%0
0081-04-047Dallas04/05/28$419,452.46ConstructionRoadwayConstructionRoadway$460,407.60$(40,955.14)-9%0
0558-03-026Abilene12/01/26$696,693.00ConstructionRoadwayConstructionRoadway$639,955.86$56,737.149%0
2374-02-166Dallas07/01/26$282,932.75ConstructionRoadwayConstructionRoadway$310,476.60$(27,543.85)-9%0
0990-02-015Corpus Christi06/02/26$30,907.60ConstructionRoadwayConstructionRoadway$33,912.76$(3,005.16)-9%0
0314-04-036Fort Worth07/01/26$346,773.76ConstructionBridgeConstructionBridge$380,384.33$(33,610.57)-9%0
1421-01-028Beaumont07/01/26$5,038,939.85ConstructionRoadwayConstructionRoadway$5,527,174.50$(488,234.65)-9%-35-1 month
0261-01-052Dallas07/01/26$677,275.50ConstructionNon RoadwayConstructionNon Roadway$742,714.35$(65,438.85)-9%0
0446-02-041Yoakum07/01/26$1,118,407.77ConstructionRoadwayConstructionRoadway$1,226,012.00$(107,604.23)-9%0
1315-01-033Dallas10/04/28$3,885,389.78ConstructionRoadwayConstructionRoadway$4,249,387.32$(363,997.54)-9%0
2033-03-011Abilene12/01/26$434,259.00ConstructionRoadwayConstructionRoadway$400,000.00$34,259.009%0
0261-02-086Dallas07/01/26$675,870.00ConstructionNon RoadwayConstructionNon Roadway$737,593.50$(61,723.50)-8%0
1562-04-016Bryan07/01/26$104,568.40ConstructionRoadwayConstructionRoadway$114,100.00$(9,531.60)-8%0
0033-06-130Abilene05/06/26$1,325,572.00ConstructionBridgeConstructionBridge$1,223,572.00$102,000.008%0
0027-08-186Houston06/02/26$311,721.35ConstructionRoadwayConstructionRoadway$287,859.62$23,861.738%0
0919-13-022Atlanta06/02/26$845,060.00ConstructionBridgeConstructionBridge$780,583.00$64,477.008%0
0978-02-085Houston07/01/26$1,325,706.60ConstructionRoadwayConstructionRoadway$1,444,405.82$(118,699.22)-8%0
2851-01-055Bryan07/01/26$50,884.35ConstructionRoadwayConstructionRoadway$47,050.00$3,834.358%0
0166-02-049Bryan07/01/26$137,319.70ConstructionRoadwayConstructionRoadway$149,130.00$(11,810.30)-8%0
0013-08-149Fort Worth07/01/27$15,928,453.33ConstructionRoadwayConstructionRoadway$17,248,438.28$(1,319,984.95)-8%0
0027-07-044Houston06/02/26$170,751.50ConstructionRoadwayConstructionRoadway$184,764.00$(14,012.50)-8%0
0918-47-537Dallas10/05/27$598,483.05ConstructionRoadwayConstructionRoadway$647,328.00$(48,844.95)-8%0
0921-02-537Pharr05/31/28$7,718,488.50ConstructionLocal LetConstructionLocal Let$8,341,667.00$(623,178.50)-7%0
0998-05-013Bryan07/01/26$56,834.35ConstructionRoadwayConstructionRoadway$61,420.00$(4,585.65)-7%0
0919-13-020Atlanta06/02/26$527,087.20ConstructionBridgeConstructionBridge$490,881.20$36,206.007%0
0836-03-075Waco09/02/26$555,819.86ConstructionRoadwayConstructionRoadway$600,000.00$(44,180.14)-7%0
0069-07-113San Angelo08/05/26$1,777,990.78ConstructionRoadwayConstructionRoadway$1,657,431.03$120,559.757%0
0138-06-047Lufkin07/01/26$59,915,665.95ConstructionRoadwayConstructionRoadway$64,563,586.26$(4,647,920.31)-7%0
0978-01-045Houston07/01/26$1,319,719.40ConstructionRoadwayConstructionRoadway$1,421,566.46$(101,847.06)-7%0
2340-02-022Atlanta01/05/28$10,125,634.00ConstructionRoadwayConstructionRoadway$9,453,804.00$671,830.007%0
0027-12-164Houston06/02/26$3,350,035.38ConstructionRoadwayConstructionRoadway$3,603,216.37$(253,180.99)-7%0
0186-03-074Bryan07/01/26$34,155.43ConstructionRoadwayConstructionRoadway$31,920.00$2,235.437%0
1973-01-021Dallas07/01/26$1,674,101.10ConstructionRoadwayConstructionRoadway$1,565,564.19$108,536.917%0
3510-04-064Houston07/01/26$3,440,293.00ConstructionNon RoadwayConstructionNon Roadway$3,693,789.00$(253,496.00)-7%0
0337-05-048Bryan09/01/27$3,278,786.69ConstructionBridgeConstructionBridge$3,518,509.97$(239,723.28)-7%0
2133-02-016Bryan07/01/26$17,500.75ConstructionRoadwayConstructionRoadway$18,780.00$(1,279.25)-7%0
0016-05-128San Antonio07/01/26$12,462,037.55ConstructionRoadwayConstructionRoadway$11,668,795.80$793,241.757%0
0919-13-021Atlanta06/02/26$495,940.80ConstructionBridgeConstructionBridge$464,576.80$31,364.007%0
0009-11-269Dallas07/01/26$268,029.00ConstructionRoadwayConstructionRoadway$287,026.95$(18,997.95)-7%0
0521-06-165San Antonio06/02/26$34,630.20ConstructionBridgeConstructionBridge$32,480.20$2,150.007%0
0492-04-034Tyler07/01/26$48,109,014.53ConstructionRoadwayConstructionRoadway$45,157,109.53$2,951,905.007%0
2993-01-011Paris06/02/26$4,600,210.40ConstructionRoadwayConstructionRoadway$4,321,251.61$278,958.796%0
0185-03-037Bryan07/01/26$71,519.04ConstructionRoadwayConstructionRoadway$76,360.00$(4,840.96)-6%0
0033-06-129Abilene05/06/26$2,130,350.40ConstructionBridgeConstructionBridge$2,003,350.40$127,000.006%0
0440-05-015Austin01/06/27$225,252,884.62ConstructionRoadwayConstructionRoadway$240,384,615.38$(15,131,730.76)-6%0
0067-18-010Lubbock06/02/26$989,073.08ConstructionRoadwayConstructionRoadway$1,054,818.08$(65,745.00)-6%0
3000-01-027Dallas07/01/26$520,281.50ConstructionRoadwayConstructionRoadway$554,545.95$(34,264.45)-6%0
0252-03-056Austin08/05/26$2,452,584.79ConstructionRoadwayConstructionRoadway$2,613,184.34$(160,599.55)-6%0
0051-03-122Houston07/01/26$722,838.60ConstructionRoadwayConstructionRoadway$770,241.06$(47,402.46)-6%0
0047-06-176Dallas07/01/26$150,126.50ConstructionRoadwayConstructionRoadway$159,793.20$(9,666.70)-6%0
0249-01-057Wichita Falls07/01/26$216,315.60ConstructionBridgeConstructionBridge$204,333.00$11,982.606%-216-7 months
0260-02-055Dallas07/01/26$542,093.50ConstructionNon RoadwayConstructionNon Roadway$575,545.95$(33,452.45)-6%0
0006-06-109Abilene06/02/26$126,022,721.70ConstructionRoadwayConstructionRoadway$119,162,496.70$6,860,225.006%0
2353-02-026Dallas05/05/27$7,573,314.29ConstructionRoadwayConstructionRoadway$7,164,411.29$408,903.006%0
0915-12-782San Antonio07/01/26$380,947.73ConstructionRoadwayConstructionRoadway$403,095.46$(22,147.73)-5%0
2452-03-128San Antonio07/01/26$180,125,212.86ConstructionRoadwayConstructionRoadway$190,314,322.00$(10,189,109.14)-5%-153-5 months
0013-08-154Fort Worth08/05/26$1,593,892.79ConstructionRoadwayConstructionRoadway$1,681,823.02$(87,930.23)-5%0
1425-03-075Pharr08/02/28$3,818,764.43ConstructionRoadwayConstructionRoadway$4,026,638.00$(207,873.57)-5%0
0921-02-538Pharr05/31/28$7,239,537.73ConstructionLocal LetConstructionLocal Let$7,626,667.00$(387,129.27)-5%0
0572-01-076Odessa05/06/26$10,581,431.98ConstructionRoadwayConstructionRoadway$11,148,066.98$(566,635.00)-5%0
0816-05-027Dallas03/01/29$10,802,563.00ConstructionRoadwayConstructionRoadway$10,285,271.43$517,291.575%0
0081-02-080Fort Worth07/01/26$459,770.00ConstructionRoadwayConstructionRoadway$483,209.50$(23,439.50)-5%0
0092-02-146Dallas07/01/26$466,949.50ConstructionRoadwayConstructionRoadway$490,515.90$(23,566.40)-5%0
1012-03-027Dallas12/01/26$8,673,294.25ConstructionRoadwayConstructionRoadway$9,106,958.96$(433,664.71)-5%-92-3 months
1012-03-028Dallas12/01/26$6,373,822.30ConstructionRoadwayConstructionRoadway$6,692,513.42$(318,691.12)-5%-92-3 months
1492-01-013Dallas12/01/26$1,331,491.45ConstructionRoadwayConstructionRoadway$1,398,066.02$(66,574.57)-5%-92-3 months
0047-14-092Dallas09/02/26$2,018,779.35ConstructionNon RoadwayConstructionNon Roadway$2,119,100.50$(100,321.15)-5%0
0786-01-095Beaumont07/01/26$4,288,248.61ConstructionRoadwayConstructionRoadway$4,500,000.00$(211,751.39)-5%-644-2 years
0581-01-179Dallas08/05/26$1,725,917.34ConstructionRoadwayConstructionRoadway$1,648,481.54$77,435.805%-300-10 months
0917-16-044Bryan08/05/26$603,666.00ConstructionBridgeConstructionBridge$577,321.07$26,344.935%0
1068-04-183Dallas08/02/28$6,789,193.62ConstructionRoadwayConstructionRoadway$7,111,311.11$(322,117.49)-5%0
0581-02-165Dallas08/04/27$9,558,816.73ConstructionRoadwayConstructionRoadway$9,144,176.22$414,640.515%0
2977-01-011Dallas07/01/26$11,777,297.44ConstructionRoadwayConstructionRoadway$12,330,496.94$(553,199.50)-4%-672-2 years
0007-02-067Abilene05/06/26$850,415.00ConstructionBridgeConstructionBridge$815,415.00$35,000.004%0
0047-06-175Dallas07/01/26$258,723.00ConstructionRoadwayConstructionRoadway$270,219.60$(11,496.60)-4%0
0712-01-052Fort Worth07/01/26$2,333,679.07ConstructionRoadwayConstructionRoadway$2,433,031.32$(99,352.25)-4%0
2846-01-008Dallas12/01/30$6,759,240.62ConstructionRoadway$6,497,917.26$261,323.364%7262 years
0047-06-178Dallas09/02/26$1,208,060.70ConstructionNon RoadwayConstructionNon Roadway$1,161,565.90$46,494.804%0
0921-02-375Pharr05/02/27$14,621,204.29ConstructionLocal LetConstructionLocal Let$15,224,166.43$(602,962.14)-4%0
0909-37-082Waco07/01/26$569,562.17ConstructionBridgeConstructionBridge$593,000.00$(23,437.83)-4%0
0917-29-152Bryan07/01/27$1,591,764.00ConstructionRoadwayConstructionRoadway$1,655,435.00$(63,671.00)-4%0
0924-06-625El Paso05/01/27$17,466,671.15ConstructionLocal LetConstructionLocal Let$18,165,338.00$(698,666.85)-4%0
0005-04-084Odessa07/01/26$5,595,705.62ConstructionRoadwayConstructionRoadway$5,400,000.00$195,705.624%0
0002-02-064El Paso11/01/28$19,632,293.75ConstructionRoadwayConstructionRoadway$20,359,415.74$(727,121.99)-4%3651 year
0915-12-786San Antonio07/01/26$373,502.68ConstructionRoadwayConstructionRoadway$387,275.16$(13,772.48)-4%0
1228-03-057Pharr05/06/26$240,864.85ConstructionRoadwayConstructionRoadway$249,764.25$(8,899.40)-4%0
0915-12-784San Antonio07/01/26$406,866.27ConstructionRoadwayConstructionRoadway$421,541.95$(14,675.68)-3%0
0908-33-115Abilene06/02/26$176,362.29ConstructionRoadwayConstructionRoadway$170,510.29$5,852.003%0
0151-02-026Austin05/06/26$9,952,848.77ConstructionRoadwayConstructionRoadway$10,279,819.07$(326,970.30)-3%0
0151-03-043Austin05/06/26$862,613.17ConstructionRoadwayConstructionRoadway$890,964.62$(28,351.45)-3%0
2121-02-189El Paso12/05/28$1,008,439.25ConstructionRoadwayConstructionRoadway$1,040,554.27$(32,115.02)-3%0
0013-10-098Fort Worth07/01/26$8,676,166.77ConstructionRoadwayConstructionRoadway$8,416,086.71$260,080.063%-153-5 months
0262-07-047Bryan07/01/26$60,498.10ConstructionRoadwayConstructionRoadway$62,410.00$(1,911.90)-3%0
0905-06-121Lubbock07/01/26$376,554.75ConstructionRoadwayConstructionRoadway$388,274.75$(11,720.00)-3%0
0915-12-752San Antonio07/01/26$356,526.40ConstructionBridgeConstructionBridge$346,526.40$10,000.003%0
0712-02-021Fort Worth07/01/26$1,297,721.50ConstructionRoadwayConstructionRoadway$1,261,648.00$36,073.503%0
0686-01-051Houston04/05/28$3,520,607.00ConstructionRoadwayConstructionRoadway$3,424,252.00$96,355.003%0
3272-01-007Lubbock06/02/26$747,382.78ConstructionRoadwayConstructionRoadway$768,682.78$(21,300.00)-3%0
0274-02-032Brownwood06/02/26$5,557,276.85ConstructionRoadwayConstructionRoadway$5,425,674.85$131,602.002%0
0675-08-117Houston05/06/26$204,710.61ConstructionRoadwayConstructionRoadway$209,670.61$(4,960.00)-2%0
0022-04-021Laredo03/01/29$10,763,000.85ConstructionRoadwayConstructionRoadway$11,022,865.35$(259,864.50)-2%35912 months
1014-03-063Dallas12/03/26$1,731,094.70ConstructionLocal LetConstructionLocal Let$1,772,766.00$(41,671.30)-2%0
0018-06-185Laredo06/02/26$63,828,090.68ConstructionRoadwayConstructionRoadway$62,373,725.73$1,454,364.952%0
0313-02-071Fort Worth04/06/27$2,070,015.37ConstructionRoadwayConstructionRoadway$2,027,259.64$42,755.732%0
0110-04-212Houston05/06/26$3,505,666.64ConstructionRoadwayConstructionRoadway$3,435,426.64$70,240.002%0
0327-07-047Pharr08/05/26$310,280.42ConstructionRoadwayConstructionRoadway$316,539.17$(6,258.75)-2%0
0540-03-039Bryan07/01/26$4,315,533.66ConstructionRoadwayConstructionRoadway$4,400,000.00$(84,466.34)-2%0
0143-04-074San Antonio06/02/26$285,741.00ConstructionBridgeConstructionBridge$280,441.00$5,300.002%0
0248-03-024Atlanta11/02/27$13,405,864.00ConstructionRoadwayUnassignedUnassigned$13,160,923.50$244,940.502%0Unassigned → Construction / Roadway
0068-01-073Lubbock07/01/26$138,352,841.20ConstructionRoadwayConstructionRoadway$135,847,883.00$2,504,958.202%-97-3 months
0185-02-042Bryan07/01/26$76,992.76ConstructionRoadwayConstructionRoadway$75,610.00$1,382.762%0
0675-08-116Houston05/06/26$1,533,541.18ConstructionRoadwayConstructionRoadway$1,562,061.18$(28,520.00)-2%0
0327-07-049Pharr08/05/26$315,468.34ConstructionRoadwayConstructionRoadway$321,317.31$(5,848.97)-2%0
0073-08-183San Antonio05/06/26$34,315,721.05ConstructionRoadwayConstructionRoadway$34,945,459.80$(629,738.75)-2%0
0192-01-103Houston06/02/26$553,663.25ConstructionRoadwayConstructionRoadway$563,765.64$(10,102.39)-2%0
0081-03-047Dallas05/06/26$111,391,860.83ConstructionRoadwayConstructionRoadway$109,560,813.58$1,831,047.252%0
0916-37-038Corpus Christi06/02/26$915,014.80ConstructionBridgeConstructionBridge$900,224.80$14,790.002%0
0747-05-043Fort Worth05/06/26$3,042,077.60ConstructionRoadwayConstructionRoadway$2,993,451.70$48,625.902%0
0720-03-153Houston06/02/26$905,283.29ConstructionRoadwayConstructionRoadway$890,994.00$14,289.292%0
1421-01-027Beaumont07/01/26$1,853,387.00ConstructionRoadwayConstructionRoadway$1,883,344.00$(29,957.00)-2%-35-1 month
0872-04-037Pharr08/05/26$305,999.93ConstructionRoadwayConstructionRoadway$310,839.61$(4,839.68)-2%0
0684-01-068Pharr03/01/27$33,950,374.48ConstructionLocal LetConstructionLocal Let$33,433,603.20$516,771.282%0
0581-02-162Dallas06/02/26$17,965,404.75ConstructionRoadwayConstructionRoadway$17,692,389.85$273,014.902%0
0917-16-042Bryan08/05/26$550,524.90ConstructionBridgeConstructionBridge$542,395.11$8,129.792%0
0686-02-030Houston04/05/28$3,267,905.00ConstructionRoadwayConstructionRoadway$3,221,150.00$46,755.001%0
0110-04-213Houston05/06/26$507,480.61ConstructionRoadwayConstructionRoadway$514,920.61$(7,440.00)-1%0
0747-05-042Fort Worth05/06/26$8,540,372.35ConstructionRoadwayConstructionRoadway$8,420,326.85$120,045.501%0
0625-01-001Waco07/01/26$2,150,632.74ConstructionRoadwayConstructionRoadway$2,180,000.00$(29,367.26)-1%0
0747-08-002Fort Worth05/06/26$5,480,400.25ConstructionRoadwayConstructionRoadway$5,554,398.25$(73,998.00)-1%0
0327-07-048Pharr08/05/26$335,989.93ConstructionRoadwayConstructionRoadway$340,335.32$(4,345.39)-1%0
1502-01-031Lubbock07/01/26$166,952,606.35ConstructionRoadwayConstructionRoadway$164,867,291.60$2,085,314.751%-97-3 months
0018-01-102Laredo05/06/26$7,425,536.19ConstructionRoadwayConstructionRoadway$7,333,506.36$92,029.831%0
0177-01-121Lufkin06/02/26$486,501.00ConstructionBridgeConstructionBridge$480,956.00$5,545.001%0
0500-03-655Houston05/06/26$8,850,867.80ConstructionBridgeConstructionBridge$8,750,914.40$99,953.401%0
0249-01-060Wichita Falls07/01/26$261,344.20ConstructionBridgeConstructionBridge$264,332.00$(2,987.80)-1%-216-7 months
1953-01-035Bryan07/01/26$77,796.65ConstructionRoadwayConstructionRoadway$76,940.00$856.651%0
0610-03-095Atlanta05/06/26$11,312,219.23ConstructionNon RoadwayConstructionNon Roadway$11,435,889.23$(123,670.00)-1%0
0110-01-059Bryan07/01/26$127,828.73ConstructionRoadwayConstructionRoadway$129,210.00$(1,381.27)-1%0
1397-01-036Dallas05/03/28$11,552,595.95ConstructionRoadwayConstructionRoadway$11,675,998.15$(123,402.20)-1%0
0327-06-031Pharr08/05/26$356,081.69ConstructionRoadwayConstructionRoadway$359,844.53$(3,762.84)-1%0
0068-01-085Lubbock06/02/26$691,133.93ConstructionRoadwayConstructionRoadway$683,933.93$7,200.001%0
0366-02-089San Antonio06/02/26$44,312,183.47ConstructionRoadwayConstructionRoadway$43,851,269.81$460,913.661%0
0068-01-084Lubbock06/02/26$705,358.23ConstructionRoadwayConstructionRoadway$698,158.23$7,200.001%0
0086-07-040Pharr08/05/26$368,950.49ConstructionRoadwayConstructionRoadway$372,629.79$(3,679.30)-1.0%0
1197-01-027Austin08/05/26$3,080,501.38ConstructionRoadwayConstructionRoadway$3,110,829.60$(30,328.22)-1.0%-154-5 months
0177-14-038Houston05/06/26$4,713,675.29ConstructionRoadwayConstructionRoadway$4,757,838.09$(44,162.80)-0.9%0
0916-26-023Corpus Christi05/06/26$1,200,909.50ConstructionBridgeConstructionBridge$1,189,809.50$11,100.000.9%0
0086-07-041Pharr08/05/26$360,110.74ConstructionRoadwayConstructionRoadway$363,332.71$(3,221.97)-0.9%0
0917-16-040Bryan08/05/26$702,786.45ConstructionBridgeConstructionBridge$708,168.67$(5,382.22)-0.8%0
0190-05-078Tyler06/02/26$1,960,952.00ConstructionRoadwayConstructionRoadway$1,975,005.00$(14,053.00)-0.7%0
0291-03-077San Antonio06/02/26$618,826.35ConstructionRoadwayConstructionRoadway$622,966.35$(4,140.00)-0.7%0
0698-03-107Pharr05/06/26$263,173.95ConstructionRoadwayConstructionRoadway$264,761.15$(1,587.20)-0.6%0
0521-06-166San Antonio06/02/26$396,200.55ConstructionBridgeConstructionBridge$393,900.55$2,300.000.6%0
0167-01-122El Paso06/02/26$84,676,469.69ConstructionRoadwayConstructionRoadway$84,225,632.19$450,837.500.5%0
0259-05-086Fort Worth07/01/26$568,444.50ConstructionRoadwayConstructionRoadway$565,694.50$2,750.000.5%-216-7 months
0167-02-093El Paso05/06/26$592,039.00ConstructionRoadwayConstructionRoadway$594,961.00$(2,922.00)-0.5%0
0327-07-050Pharr08/05/26$405,710.18ConstructionRoadwayConstructionRoadway$407,530.22$(1,820.04)-0.5%0
0038-01-104Laredo02/02/28$2,615,401.95ConstructionRoadwayConstructionRoadway$2,604,201.43$11,200.520.4%-365-1 year
0025-02-230San Antonio06/02/26$504,445.00ConstructionBridgeConstructionBridge$502,495.00$1,950.000.4%0
1064-01-048Pharr05/06/26$200,859.55ConstructionRoadwayConstructionRoadway$200,135.05$724.500.4%0
1586-01-093Pharr05/06/26$177,905.35ConstructionRoadwayConstructionRoadway$177,268.35$637.000.4%0
0220-01-039Pharr05/06/26$293,896.05ConstructionRoadwayConstructionRoadway$293,029.05$867.000.3%0
0038-07-085Pharr05/06/26$232,444.80ConstructionRoadwayConstructionRoadway$231,845.30$599.500.3%0
0859-04-018Bryan07/01/26$53,671.70ConstructionRoadwayConstructionRoadway$53,540.00$131.700.3%0
2094-01-063Pharr05/06/26$33,933,190.86ConstructionRoadwayConstructionRoadway$33,850,470.86$82,720.000.2%0
1401-01-024Bryan07/01/26$109,702.55ConstructionRoadwayConstructionRoadway$109,910.00$(207.45)-0.2%0
0018-05-089Laredo06/01/27$256,120,160.76ConstructionRoadwayConstructionRoadway$255,671,664.26$448,496.500.2%0
0167-01-137El Paso06/02/26$1,188,375.00ConstructionRoadwayConstructionRoadway$1,186,375.00$2,000.000.2%0
2121-03-167El Paso05/06/26$1,166,135.50ConstructionRoadwayConstructionRoadway$1,167,991.50$(1,856.00)-0.2%0
0018-06-219Laredo05/06/26$4,845,177.97ConstructionRoadwayConstructionRoadway$4,838,092.97$7,085.000.1%0
0050-12-002Houston06/02/26$785,715.19ConstructionRoadwayConstructionRoadway$786,825.43$(1,110.24)-0.1%0
0276-07-035San Antonio09/02/26$8,601,216.47ConstructionRoadwayConstructionRoadway$8,610,648.49$(9,432.02)-0.1%0
0019-01-153Fort Worth07/01/26$1,566,691.63ConstructionRoadwayConstructionRoadway$1,565,041.53$1,650.100.1%-216-7 months
0630-01-059Pharr05/06/26$64,925.00ConstructionRoadwayConstructionRoadway$64,985.00$(60.00)-0.1%0
0521-04-285San Antonio05/06/26$131,056,485.41ConstructionRoadwayConstructionRoadway$131,153,285.41$(96,800.00)-0.1%0
0521-04-286San Antonio05/06/26$131,056,485.41Joint Bid UtilityRight-of-WayJoint Bid UtilityRight-of-Way$131,153,285.41$(96,800.00)-0.1%0
0937-01-027Lufkin06/02/26$5,065,573.30ConstructionRoadwayConstructionRoadway$5,062,782.80$2,790.500.1%0
0255-06-073Pharr05/06/26$73,884,136.67ConstructionRoadwayConstructionRoadway$73,911,736.67$(27,600.00)-0.04%0
0001-02-081El Paso11/01/28$801,308.04ConstructionRoadwayConstructionRoadway$801,308.00$0.040%0
0207-05-089Atlanta10/05/27$3,526,729.00ConstructionBridgeConstructionBridge$3,526,728.76$0.240%0
0843-07-026Atlanta10/05/27$4,036,208.00ConstructionBridgeConstructionBridge$4,036,207.70$0.300%0
0843-07-027Atlanta10/05/27$5,470,641.00ConstructionBridgeConstructionBridge$5,470,640.94$0.060%0
1575-03-021Atlanta10/05/27$3,576,073.00ConstructionBridgeConstructionBridge$3,576,073.03$(0.03)0%0
0917-16-041Bryan08/05/26$607,979.40ConstructionBridgeConstructionBridge$607,989.40$(10.00)0%0
0880-04-040Lubbock05/06/26$10,274,387.05ConstructionRoadwayConstructionRoadway$10,274,814.05$(427.00)0%0
454 rows · download CSV

Putting It Together

This latest analysis underscores that the TxDOT pipeline is expanding with a growing number of projects and increasing overall costs, despite a drift in project timelines pushing many deadlines further out.


Final Takeaway

This pattern suggests a cautious approach to moving forward with infrastructure projects, emphasizing the importance of careful planning and resource allocation.